Unexpected engineering works: Amersfoort-Zwolle (6 January 2018)
-
Disruption resolved Last update
Between Putten and Nunspeet the train traffic is fully resumed.
-
Delays decreasing
Between Putten and Nunspeet the restrictions are resolved.
Delays are decreasing.
This will take until approximately 8:30 PM hours. -
Delays decreasing
Between Putten and Nunspeet the restrictions are resolved.
Delays are decreasing.
This will take until approximately 8:30 PM hours.Advice
Local buses are running between Nunspeet, Harderwijk, Ermelo and Putten.
Train measures
- Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Amersfoort and Zwolle
- Sprinter 5600 Utrecht C. - Amersfoort - Zwolle is cancelled between Putten and 't Harde
-
Update
Between Putten and Nunspeet no trains are running due to unexpected engineering works.
This will take until approximately 8:30 PM hours.Advice
Local buses are running between Nunspeet, Harderwijk, Ermelo and Putten.
Train measures
- Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Amersfoort and Zwolle
- Sprinter 5600 Utrecht C. - Amersfoort - Zwolle is cancelled between Putten and 't Harde
-
Disruption
Between Putten and Nunspeet no trains are running due to unexpected engineering works.
This will take until approximately 8:30 PM hours.
More about this disruption
Statistics
This disruption started at 6:54 PM on January 6, 2018 and took 1 hour, 34 minutes in total.
For statistics, this disruption is caused due to unexpected engineering works.
Operators
This disruption affects trains operated by NS.