defecte bovenleiding

Damaged overhead wires: Zwolle-Emmen (19 February 2018)

  1. Disruption resolved Last update

    Between Gramsbergen and Coevorden the train traffic is fully resumed.

  2. Delays decreasing

    Between Gramsbergen and Coevorden the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 9:30 PM hours.

  3. Delays decreasing

    Between Gramsbergen and Coevorden the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 9:30 PM hours.

    Advice

    Local buses are still running between Coevorden and Gramsbergen.

  4. Delays decreasing

    Between Gramsbergen and Coevorden the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 9:30 PM hours.

    Advice

    Local buses are still running between Coevorden and Gramsbergen.

    Train measures

    • Sneltrein 3800 Zwolle - Emmen is cancelled between Gramsbergen and Coevorden
    • Stoptrein 8000 Zwolle - Emmen is cancelled between Gramsbergen and Coevorden
    • Sneltrein 13800 Zwolle - Coevorden is cancelled between Gramsbergen and Coevorden
  5. Update

    Between Gramsbergen and Coevorden no trains are running due to damaged overhead wires.
    The extra travel time may be up to 60 minutes.
    This will take until approximately 9:30 PM hours.

    Advice

    Local buses are running between Coevorden and Gramsbergen.

    Train measures

    • Sneltrein 3800 Zwolle - Emmen is cancelled between Gramsbergen and Coevorden
    • Stoptrein 8000 Zwolle - Emmen is cancelled between Gramsbergen and Coevorden
    • Sneltrein 13800 Zwolle - Coevorden is cancelled between Gramsbergen and Coevorden
  6. Update

    Between Gramsbergen and Coevorden no trains are running due to damaged overhead wires.
    The extra travel time may be up to 60 minutes.
    This will take until approximately 11:10 PM hours.

    Advice

    Local buses are running between Coevorden and Gramsbergen.

    Train measures

    • Sneltrein 3800 Zwolle - Emmen is cancelled between Gramsbergen and Coevorden
    • Stoptrein 8000 Zwolle - Emmen is cancelled between Gramsbergen and Coevorden
    • Sneltrein 13800 Zwolle - Coevorden is cancelled between Gramsbergen and Coevorden
  7. Update

    Between Gramsbergen and Coevorden no trains are running due to damaged overhead wires.
    The extra travel time may be up to 60 minutes.
    This will take until approximately 11:10 PM hours.

    Train measures

    • Sneltrein 3800 Zwolle - Emmen is cancelled between Gramsbergen and Coevorden
    • Stoptrein 8000 Zwolle - Emmen is cancelled between Gramsbergen and Coevorden
    • Sneltrein 13800 Zwolle - Coevorden is cancelled between Gramsbergen and Coevorden
  8. Update

    Between Gramsbergen and Coevorden no trains are running due to damaged overhead wires.
    The extra travel time may be up to 60 minutes.
    It is not known yet how long this will take.

    Train measures

    • Sneltrein 3800 Zwolle - Emmen is cancelled between Gramsbergen and Coevorden
    • Stoptrein 8000 Zwolle - Emmen is cancelled between Gramsbergen and Coevorden
    • Sneltrein 13800 Zwolle - Coevorden is cancelled between Gramsbergen and Coevorden
  9. Update

    Between Gramsbergen and Coevorden no trains are running due to damaged overhead wires.
    It is not known yet how long this will take.

  10. Disruption

    Between Gramsbergen and Coevorden there is a service disruption due to damaged overhead wires.
    Updates will follow as more information becomes available.

More about this disruption

Statistics

This disruption started at 6:23 PM on February 19, 2018 and took 3 hours, 4 minutes in total.

For statistics, this disruption is caused due to damaged overhead wires.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by Arriva and Blauwnet.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights