seinstoring

Signal failure: Utrecht-Rhenen (25 March 2019)

  1. Disruption resolved Last update

    Between Utrecht Centraal and Maarn the restrictions are resolved.

    Advice

    Local buses are still running between Bunnik and Maarn.

  2. Delays decreasing

    Between Utrecht Centraal and Maarn the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 9:30 AM hours.

    Advice

    Local buses are still running between Bunnik and Maarn.

  3. Delays decreasing

    Between Utrecht Centraal and Maarn the restrictions are resolved.
    Delays are decreasing.
    This will take until approximately 9:30 AM hours.

    Advice

    Local buses are still running between Bunnik and Maarn.

  4. Update

    Between Utrecht Centraal and Maarn no Sprinters are running due to a signal failure.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 11:00 AM hours.

    Advice

    Local buses are running between Bunnik and Maarn.

    Train measures

    • Sprinter 7300 Veenendaal C. - Utrecht C. - Breukelen is cancelled between Utrecht Centraal and Maarn
    • Sprinter 7400 Uitgeest - Amsterdam C. - Utrecht C. - Rhenen is cancelled between Utrecht Centraal and Maarn
  5. Update

    Between Utrecht Centraal and Maarn no Sprinters are running due to a signal failure.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 9:30 AM hours.

    Advice

    Local buses are running between Bunnik and Maarn.

    Train measures

    • Sprinter 7300 Veenendaal C. - Utrecht C. - Breukelen is cancelled between Utrecht Centraal and Maarn
    • Sprinter 7400 Uitgeest - Amsterdam C. - Utrecht C. - Rhenen is cancelled between Utrecht Centraal and Maarn
  6. Update

    Between Utrecht Centraal and Maarn no Sprinters are running due to a signal failure.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 9:30 AM hours.

    Train measures

    • Sprinter 7300 Veenendaal C. - Utrecht C. - Breukelen is cancelled between Utrecht Centraal and Maarn
    • Sprinter 7400 Uitgeest - Amsterdam C. - Utrecht C. - Rhenen is cancelled between Utrecht Centraal and Maarn
  7. Update

    Between Utrecht Centraal and Maarn no Sprinters are running due to a signal failure.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 9:00 AM hours.

    Train measures

    • Sprinter 7300 Veenendaal C. - Utrecht C. - Breukelen is cancelled between Utrecht Centraal and Maarn
    • Sprinter 7400 Uitgeest - Amsterdam C. - Utrecht C. - Rhenen is cancelled between Utrecht Centraal and Maarn
  8. Update

    Between Utrecht Centraal and Maarn far fewer trains are running due to a signal failure.
    This will take until approximately 9:00 AM hours.

    Train measures

    • Sprinter 7300 Veenendaal C. - Utrecht C. - Breukelen is cancelled between Utrecht Centraal and Maarn
    • Sprinter 7400 Uitgeest - Amsterdam C. - Utrecht C. - Rhenen is cancelled between Utrecht Centraal and Maarn
  9. Update

    Between Utrecht Centraal and Maarn there are fewer trains running due to a signal failure.
    This will take until approximately 9:00 AM hours.

  10. Disruption

    Between Utrecht Centraal and Maarn far fewer trains are running due to a signal failure.
    This will take until approximately 9:00 AM hours.

More about this disruption

Statistics

This disruption started at 6:26 AM on March 25, 2019 and took 3 hours, 1 minute in total.

For statistics, this disruption is caused due to a signal failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS and NS International.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights