Points failure: Rotterdam-Breda (HSL) (19 March 2020)
-
Disruption resolved Last update
Between Rotterdam Centraal and Breda the train traffic is fully resumed.
Train measures
- Intercity 1100 Den Haag C. - Rotterdam C. - Breda is diverted between Rotterdam Centraal and Dordrecht
-
Delays decreasing
Between Rotterdam Centraal and Breda the restrictions are resolved.
Delays are decreasing.
Service is normal around 4:00 PM hours.Train measures
- Intercity 1100 Den Haag C. - Rotterdam C. - Breda is diverted between Rotterdam Centraal and Dordrecht
-
Update
Between Rotterdam Centraal and Breda trains are running via an alternative route due to a points failure.
The extra travel time is about 30 minutes.
This will take until approximately 5:00 PM hours.Train measures
- Intercity 1100 Den Haag C. - Rotterdam C. - Breda is diverted between Rotterdam Centraal and Dordrecht
-
Update
Between Rotterdam Centraal and Breda trains are running via an alternative route due to a points failure.
The extra travel time is about 30 minutes.
This will take until approximately 5:00 PM hours. -
Update
Between Rotterdam Centraal and Breda fewer trains are running on the high-speed line due to a points failure.
The extra travel time is about 30 minutes.
This will take until approximately 5:00 PM hours. -
Update
Between Rotterdam Centraal and Breda trains are running via an alternative route due to a points failure.
The extra travel time is about 30 minutes.
This will take until approximately 5:00 PM hours. -
Update
Between Rotterdam Centraal and Breda fewer trains are running on the high-speed line due to a points failure.
This will take until approximately 5:00 PM hours. -
Update
Between Rotterdam Centraal and Breda there are fewer trains running due to a points failure.
This will take until approximately 5:00 PM hours. -
Disruption
Between Rotterdam Centraal and Breda there is a service disruption due to a points failure.
Updates will follow as more information becomes available.
More about this disruption
Statistics
This disruption started at 2:24 PM on March 19, 2020 and took 1 hour, 37 minutes in total.
For statistics, this disruption is caused due to a points failure.
Operators
This disruption affects trains operated by NS and NS International.
Got delayed due to this disruption? You may be reimbursed.