wisselstoring

Points failure: Den Haag-Rotterdam (6 August 2020)

  1. Disruption resolved Last update

    Between Den Haag Centraal and Schiedam Centrum the train traffic is fully resumed.

  2. Delays decreasing

    Between Den Haag Centraal and Schiedam Centrum the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 9:10 PM hours.

  3. Update

    Between Den Haag Centraal and Schiedam Centrum fewer Sprinter trains are running due to a points failure.
    The extra travel time may be up to 15 minutes.
    This will take until approximately 9:30 PM hours.

    Train measures

    • Sprinter 5500 Utrecht C. - Baarn is cancelled between Den Haag Centraal and Rotterdam Centraal
  4. Update

    Between Den Haag Centraal and Schiedam Centrum fewer Sprinter trains are running due to a points failure.
    The extra travel time may be up to 15 minutes.
    This will take until approximately 9:30 PM hours.

  5. Update

    Between Den Haag Centraal and Schiedam Centrum fewer Sprinter trains are running due to a points failure.
    The extra travel time may be up to 15 minutes.
    This will take until approximately 7:30 PM hours.

  6. Disruption

    Between Delft and Den Haag HS there are fewer trains running due to a points failure.
    This will take until approximately 7:30 PM hours.

More about this disruption

Statistics

This disruption started at 4:55 PM on August 6, 2020 and took 4 hours, 17 minutes in total.

For statistics, this disruption is caused due to a points failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights