Person on the railway track: Nijmegen-'s-Hertogenbosch (6 November 2020)
-
Disruption resolved Last update
Between Ravenstein and Oss the train traffic is fully resumed.
-
Delays decreasing
Between Ravenstein and Oss the restrictions are resolved.
Delays are decreasing.
Service is normal around 2:30 PM hours. -
Update
Between Ravenstein and Oss no trains are running due to a person on the railway track.
This will take until approximately 3:30 PM hours. -
Disruption
Between 's-Hertogenbosch and Oss there is a service disruption due to a person on the railway track.
Updates will follow as more information becomes available.
More about this disruption
Statistics
This disruption started at 1:47 PM on November 6, 2020 and took 39 minutes in total.
For statistics, this disruption is caused due to a person on the railway track.
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.