uitloop werkzaamheden

Over-running engineering works: Amersfoort Centraal (19 January 2021)

  1. Disruption resolved Last update

    From and to Amersfoort Centraal the train traffic is fully resumed.

  2. Delays decreasing

    From and to Amersfoort Centraal the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 7:30 AM hours.

  3. Update

    From and to Amersfoort Centraal there are fewer trains running due to over-running engineering works.
    This will take until approximately 7:30 AM hours.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Utrecht Centraal and Zwolle
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Utrecht Centraal and Zwolle
    • Intercity 1500 Amsterdam C. - Amersfoort C. is cancelled between Amsterdam Centraal and Deventer
    • Intercity 1700 Den Haag C. - Amersfoort C. - Hengelo - Enschede is cancelled between Utrecht Centraal and Apeldoorn
    • Intercity 11600 Schiphol Airport - Amersfoort C. - Schothorst is cancelled between Hilversum and Amersfoort Schothorst
    • Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Utrecht Centraal and Amersfoort Schothorst
    • Sprinter 15800 Amsterdam C. - Vathorst is cancelled between Baarn and Amersfoort Schothorst
    • Stoptrein 31300 Amersfoort C. - Ede-Wageningen is cancelled between Amersfoort Centraal and Barneveld Centrum
  4. Update

    From and to Amersfoort Centraal no trains are running due to over-running engineering works.
    This will take until approximately 7:30 AM hours.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Utrecht Centraal and Zwolle
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Utrecht Centraal and Zwolle
    • Intercity 1500 Amsterdam C. - Amersfoort C. is cancelled between Amsterdam Centraal and Deventer
    • Intercity 1700 Den Haag C. - Amersfoort C. - Hengelo - Enschede is cancelled between Utrecht Centraal and Apeldoorn
    • Intercity 11600 Schiphol Airport - Amersfoort C. - Schothorst is cancelled between Hilversum and Amersfoort Schothorst
    • Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Utrecht Centraal and Amersfoort Schothorst
    • Sprinter 15800 Amsterdam C. - Vathorst is cancelled between Baarn and Amersfoort Schothorst
    • Stoptrein 31300 Amersfoort C. - Ede-Wageningen is cancelled between Amersfoort Centraal and Barneveld Centrum
  5. Update

    From and to Amersfoort Centraal no trains are running due to over-running engineering works.
    This will take until approximately 6:30 AM hours.

  6. Update

    From and to Amersfoort Centraal there are delays and fewer trains are running due to over-running engineering works.
    This will take until approximately 6:30 AM hours.

  7. Update

    From and to Amersfoort Centraal no trains are running due to over-running engineering works.
    This will take until approximately 6:30 AM hours.

  8. Disruption

    From and to Amersfoort Centraal there are delays and fewer trains are running due to over-running engineering works.
    This will take until approximately 6:30 AM hours.

More about this disruption

Statistics

This disruption started at 5:00 AM on January 19, 2021 and took 2 hours, 29 minutes in total.

For statistics, this disruption is caused due to over-running engineering works.

Operators

This disruption affects trains operated by NS, NS International and Connexxion.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights