Over-running engineering works: Leeuwarden-Harlingen Haven (21 April 2021)
-
Disruption resolved Last update
Between Leeuwarden and Harlingen the train traffic is fully resumed.
-
Delays decreasing
Between Leeuwarden and Harlingen the restrictions are resolved.
Delays are decreasing.
Service is normal around 6:30 AM hours. -
Update
Between Leeuwarden and Harlingen no trains are running due to over-running engineering works.
The extra travel time is more than 60 minutes.
This will take until approximately 6:30 AM hours. -
Disruption
Between Leeuwarden and Harlingen no trains are running due to over-running engineering works.
The extra travel time is more than 60 minutes.
This will take until approximately 7:15 AM hours.
More about this disruption
Statistics
This disruption started at 5:27 AM on April 21, 2021 and took 1 hour, 2 minutes in total.
For statistics, this disruption is caused due to over-running engineering works.
Operators
This disruption affects trains operated by Arriva.
Got delayed due to this disruption? You may be reimbursed.