Points failure: Amersfoort-Zwolle (24 April 2021)
-
Disruption resolved Last update
Between Amersfoort Centraal and Amersfoort Schothorst the train traffic is fully resumed.
-
Delays decreasing
Between Amersfoort Centraal and Amersfoort Schothorst the restrictions are resolved.
Delays are decreasing.
Service is normal around 6:00 PM hours.Train measures
- Intercity 11600 Schiphol Airport - Amersfoort C. - Schothorst is cancelled between Amersfoort Centraal and Amersfoort Schothorst
- Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Amersfoort Centraal and Amersfoort Schothorst
-
Update
Between Amersfoort Centraal and Amersfoort Schothorst no intercities are running due to a points failure.
The extra travel time is more than 15 minutes.
Service is normal around 6:00 PM hours.Train measures
- Intercity 11600 Schiphol Airport - Amersfoort C. - Schothorst is cancelled between Amersfoort Centraal and Amersfoort Schothorst
- Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Amersfoort Centraal and Amersfoort Schothorst
-
Update
Between Amersfoort Centraal and Amersfoort Schothorst no intercities are running due to a points failure.
The extra travel time is more than 15 minutes.
This will take until approximately 6:30 PM hours.Train measures
- Intercity 11600 Schiphol Airport - Amersfoort C. - Schothorst is cancelled between Amersfoort Centraal and Amersfoort Schothorst
- Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Amersfoort Centraal and Amersfoort Schothorst
-
Disruption
Between Amersfoort Centraal and Amersfoort Schothorst no intercities are running due to a points failure.
This will take until approximately 6:30 PM hours.Train measures
- Intercity 11600 Schiphol Airport - Amersfoort C. - Schothorst is cancelled between Amersfoort Centraal and Amersfoort Schothorst
- Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Amersfoort Centraal and Amersfoort Schothorst
More about this disruption
Statistics
This disruption started at 12:23 PM on April 24, 2021 and took 5 hours, 32 minutes in total.
For statistics, this disruption is caused due to a points failure.
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.