wisselstoring

Points failure: Amersfoort-Zwolle (16 November 2021)

  1. Disruption resolved Last update

    Between Amersfoort Centraal and Zwolle the train traffic is fully resumed.

  2. Delays decreasing

    Between Amersfoort Centraal and Zwolle the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 11:00 PM hours.

  3. Update

    Between Amersfoort Centraal and Zwolle far fewer trains are running due to a points failure.
    This will take until approximately 11:00 PM hours.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Amersfoort Centraal and Zwolle
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Amersfoort Centraal and Zwolle
    • Sprinter 5600 Utrecht C. - Amersfoort C. - Zwolle runs only once per hour between 't Harde and Zwolle
  4. Update

    Between Amersfoort Centraal and Zwolle far fewer trains are running due to a points failure.
    This will take until approximately 11:00 PM hours.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen runs only once per hour between Amersfoort Centraal and Zwolle
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden runs only once per hour between Amersfoort Centraal and Zwolle
    • Sprinter 5600 Utrecht C. - Amersfoort C. - Zwolle runs only once per hour between 't Harde and Zwolle
  5. Update

    Between Amersfoort Centraal and Zwolle far fewer trains are running due to a points failure.
    This will take until approximately 10:30 PM hours.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen runs only once per hour between Amersfoort Centraal and Zwolle
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden runs only once per hour between Amersfoort Centraal and Zwolle
    • Sprinter 5600 Utrecht C. - Amersfoort C. - Zwolle runs only once per hour between 't Harde and Zwolle
  6. Update

    Between Amersfoort Centraal and Zwolle far fewer trains are running due to a points failure.
    This will take until approximately 9:30 PM hours.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen runs only once per hour between Amersfoort Centraal and Zwolle
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden runs only once per hour between Amersfoort Centraal and Zwolle
    • Sprinter 5600 Utrecht C. - Amersfoort C. - Zwolle runs only once per hour between 't Harde and Zwolle
  7. Update

    Between Amersfoort Centraal and Zwolle far fewer trains are running due to a points failure.
    This will take until approximately 8:30 PM hours.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen runs only once per hour between Amersfoort Centraal and Zwolle
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden runs only once per hour between Amersfoort Centraal and Zwolle
    • Sprinter 5600 Utrecht C. - Amersfoort C. - Zwolle runs only once per hour between 't Harde and Zwolle
  8. Update

    Between Amersfoort Centraal and Zwolle far fewer trains are running due to a points failure.
    This will take until approximately 8:30 PM hours.

  9. Update

    Between 't Harde and Zwolle far fewer trains are running due to a points failure.
    This will take until approximately 8:30 PM hours.

  10. Disruption

    Between Zwolle and 't Harde there is a service disruption due to a points failure.
    Updates will follow as more information becomes available.

More about this disruption

Statistics

This disruption started at 6:04 PM on November 16, 2021 and took 5 hours, 1 minute in total.

For statistics, this disruption is caused due to a points failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights