defecte bovenleiding

Damaged overhead wires: Amersfoort-Zwolle (5 January 2022)

  1. Disruption resolved Last update

    Between Amersfoort Centraal and Zwolle the train traffic is fully resumed.

  2. Delays decreasing

    Between Amersfoort Centraal and Zwolle the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 2:30 PM hours.

  3. Disruption resolved

    Between Amersfoort Centraal and Zwolle the train traffic is fully resumed.

  4. Delays decreasing

    Between Amersfoort Centraal and Zwolle the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 1:30 PM hours.

  5. Update

    Between Amersfoort Centraal and Zwolle no intercities are running due to damaged overhead wires.
    This will take until approximately 1:30 PM hours.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Utrecht Centraal and Zwolle
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Utrecht Centraal and Zwolle
  6. Update

    Between Amersfoort Centraal and Zwolle no intercities are running due to damaged overhead wires.
    This will take until approximately 2:00 PM hours.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Utrecht Centraal and Zwolle
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Utrecht Centraal and Zwolle
  7. Update

    Between Amersfoort Centraal and Zwolle no intercities are running due to damaged overhead wires.
    This will take until approximately 4:30 PM hours.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Utrecht Centraal and Zwolle
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Utrecht Centraal and Zwolle
  8. Update

    Between Amersfoort Centraal and Zwolle no intercities are running due to damaged overhead wires.
    This will take until approximately 3:30 PM hours.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Utrecht Centraal and Zwolle
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Utrecht Centraal and Zwolle
  9. Disruption

    Between Putten and Harderwijk there are fewer trains running due to damaged overhead wires.
    This will take until approximately 3:30 PM hours.

More about this disruption

Statistics

This disruption started at 11:10 AM on January 5, 2022 and took 3 hours, 16 minutes in total.

For statistics, this disruption is caused due to damaged overhead wires.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights