overwegstoring

Level crossing failure: Sittard-Heerlen (1 July)

  1. Disruption resolved Last update

    Between Sittard and Heerlen the train traffic is fully resumed.

  2. Delays decreasing

    Between Sittard and Heerlen the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 2:30 PM hours.

  3. Update

    Between Sittard and Heerlen there are fewer trains running due to a level crossing failure.
    Service is normal around 2:30 PM hours.

    Train measures

    • Intercity 3900 Enkhuizen/Heerlen - Heerlen/Enkhuizen runs only once per hour between Heerlen and Sittard
    • Stoptrein 32500 Sittard/Heerlen - Heerlen/Sittard runs only once per hour between Heerlen and Sittard
  4. Update

    Between Sittard and Heerlen there are fewer trains running due to a level crossing failure.
    This will take until approximately 2:30 PM hours.

    Train measures

    • Intercity 3900 Enkhuizen/Heerlen - Heerlen/Enkhuizen runs only once per hour between Heerlen and Sittard
    • Stoptrein 32500 Sittard/Heerlen - Heerlen/Sittard runs only once per hour between Heerlen and Sittard
  5. Update

    Between Sittard and Heerlen there are fewer trains running due to a level crossing failure.
    This will take until approximately 3:00 PM hours.

    Train measures

    • Intercity 3900 Enkhuizen/Heerlen - Heerlen/Enkhuizen runs only once per hour between Heerlen and Sittard
    • Stoptrein 32500 Sittard/Heerlen - Heerlen/Sittard runs only once per hour between Heerlen and Sittard
  6. Update

    Between Sittard and Heerlen there are fewer trains running due to a level crossing failure.
    This will take until approximately 2:30 PM hours.

    Train measures

    • Intercity 3900 Enkhuizen/Heerlen - Heerlen/Enkhuizen runs only once per hour between Heerlen and Sittard
    • Stoptrein 32500 Sittard/Heerlen - Heerlen/Sittard runs only once per hour between Heerlen and Sittard
  7. Update

    Between Sittard and Heerlen there are fewer trains running due to a level crossing failure.
    This will take until approximately 1:30 PM hours.

    Train measures

    • Intercity 3900 Enkhuizen/Heerlen - Heerlen/Enkhuizen runs only once per hour between Heerlen and Sittard
    • Stoptrein 32500 Sittard/Heerlen - Heerlen/Sittard runs only once per hour between Heerlen and Sittard
  8. Update

    Between Sittard and Heerlen there are fewer trains running due to a level crossing failure.
    This will take until approximately 2:30 PM hours.

    Train measures

    • Intercity 3900 Heerlen/Enkhuizen - Enkhuizen/Heerlen runs only once per hour between Heerlen and Sittard
    • Stoptrein 32500 Heerlen/Sittard - Sittard/Heerlen runs only once per hour between Heerlen and Sittard
  9. Update

    Between Sittard and Heerlen there are fewer trains running due to a level crossing failure.
    This will take until approximately 2:30 PM hours.

    Train measures

    • Intercity 3900 Enkhuizen/Heerlen - Heerlen/Enkhuizen runs less often between Heerlen and Sittard
    • Stoptrein 32500 Sittard/Heerlen - Heerlen/Sittard runs less often between Heerlen and Sittard
  10. Update

    Between Sittard and Heerlen there are fewer trains running due to a level crossing failure.
    This will take until approximately 2:30 PM hours.

  11. Update

    Between Sittard and Heerlen there is a service disruption due to a level crossing failure.
    This will take until approximately 2:30 PM hours.

  12. Disruption

    Between Sittard and Heerlen there is a service disruption due to a level crossing failure.
    It is not known yet how long this will take.

More about this disruption

Statistics

This disruption started at 11:18 AM on July 1, 2024 and took 3 hours, 16 minutes in total.

For statistics, this disruption is caused due to a level crossing failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS and Arriva.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights