Level crossing failure: Amersfoort-Zwolle (15 August)
-
Disruption resolved Last update
Between Amersfoort Vathorst and Putten the train traffic is fully resumed.
-
Delays decreasing
Between Amersfoort Vathorst and Putten the restrictions are resolved.
Delays are decreasing.
Service is normal around 10:30 AM hours. -
Delays decreasing
Between Amersfoort Vathorst and Putten the restrictions are resolved.
Delays are decreasing.
Service is normal around 10:45 AM hours. -
Update
Between Amersfoort Vathorst and Putten no trains are running due to a level crossing failure.
This will take until approximately 10:45 AM hours. -
Update
Between Amersfoort Vathorst and Putten no trains are running due to a level crossing failure.
This will take until approximately 12:00 PM hours. -
Update
Between Amersfoort Centraal and Harderwijk there are delays and fewer trains are running due to a level crossing failure.
This will take until approximately 12:00 PM hours. -
Update
Between Amersfoort Centraal and Harderwijk no trains are running due to a level crossing failure.
This will take until approximately 12:00 PM hours. -
Disruption
Between Amersfoort Centraal and Harderwijk there is a service disruption due to a level crossing failure.
This will take until approximately 12:00 PM hours.
More about this disruption
Statistics
This disruption started at 9:30 AM on August 15, 2024 and took 53 minutes in total.
For statistics, this disruption is caused due to a level crossing failure.
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.