Level crossing failure: Amersfoort - Ede-Wageningen; Amersfoort - Barneveld (2 October)
-
Disruption resolved Last update
Between Amersfoort Centraal and Barneveld Zuid the train traffic is fully resumed.
-
Delays decreasing
Between Amersfoort Centraal and Barneveld Zuid the restrictions are resolved.
Delays are decreasing.
Service is normal around 11:30 AM hours. -
Update
Between Amersfoort Centraal and Barneveld Zuid far fewer trains are running due to a level crossing failure.
This will take until approximately 11:30 AM hours. -
Update
Between Amersfoort Centraal and Barneveld Centrum far fewer trains are running due to a level crossing failure.
This will take until approximately 11:30 AM hours. -
Update
Between Amersfoort Centraal and Barneveld Centrum far fewer trains are running due to a level crossing failure.
This will take until approximately 11:00 AM hours. -
Disruption
Between Amersfoort Centraal and Barneveld Centrum there are delays and fewer trains are running due to a level crossing failure.
This will take until approximately 11:00 AM hours.
More about this disruption
Statistics
This disruption started at 10:15 AM on October 2, 2024 and took 1 hour, 12 minutes in total.
For statistics, this disruption is caused due to a level crossing failure.
Operators
This disruption affects trains operated by Keolis and RRReis.