Power failure: Amsterdam-Utrecht; Amsterdam-Gouda (24 January 2017)
-
Disruption resolved Last update
Between Abcoude and Breukelen the train traffic is fully resumed.
-
Delays decreasing
Between Abcoude and Breukelen the restrictions are resolved.
Delays are decreasing.
Service is normal around 8:15 AM hours. -
Update
Between Abcoude and Breukelen there are delays and fewer trains are running due to a power failure.
It is not known yet how long this will take. -
Disruption
Between Abcoude and Breukelen no trains are running due to a power failure.
It is not known yet how long this will take.
More about this disruption
Statistics
This disruption started at 7:53 AM on January 24, 2017 and took 21 minutes in total.
For statistics, this disruption is caused due to a power failure.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS and NS International.
Got delayed due to this disruption? You may be reimbursed.