wisselstoring

Points failure: Utrecht-Rotterdam; Utrecht-Den Haag (25 February 2017)

  1. Disruption resolved Last update

    Between Utrecht Centraal and Rotterdam Centraal the train traffic is fully resumed.
    Between Utrecht Centraal and Den Haag Centraal the train traffic is fully resumed.

  2. Delays decreasing

    Between Utrecht Centraal and Rotterdam Centraal the restrictions are resolved.
    Between Utrecht Centraal and Den Haag Centraal the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 6:15 PM hours.

  3. Update

    Between Utrecht Centraal and Rotterdam Centraal fewer intercities are running due to a points failure.
    Between Utrecht Centraal and Den Haag Centraal fewer intercities are running due to a points failure.
    Service is normal around 6:15 PM hours.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Utrecht Centraal and Rotterdam Centraal
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Utrecht Centraal and Rotterdam Centraal
    • Intercity 2000 Den Haag C. - Utrecht C. is cancelled between Den Haag Centraal and Utrecht Centraal
  4. Update

    Between Utrecht Centraal and Rotterdam Centraal fewer intercities are running due to a points failure.
    Between Utrecht Centraal and Den Haag Centraal fewer intercities are running due to a points failure.
    This will take until approximately 6:15 PM hours.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Utrecht Centraal and Rotterdam Centraal
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Utrecht Centraal and Rotterdam Centraal
    • Intercity 2000 Den Haag C. - Utrecht C. is cancelled between Den Haag Centraal and Utrecht Centraal
  5. Update

    Between Utrecht Centraal and Rotterdam Centraal fewer intercities are running due to a points failure.
    Between Utrecht Centraal and Den Haag Centraal fewer intercities are running due to a points failure.
    This will take until approximately 6:15 PM hours.

  6. Disruption

    Between Utrecht Centraal and Rotterdam Centraal fewer intercities are running due to a points failure.
    Between Utrecht Centraal and Den Haag Centraal fewer intercities are running due to a points failure.
    It is not known yet how long this will take.

More about this disruption

Statistics

This disruption started at 3:46 PM on February 25, 2017 and took 2 hours, 29 minutes in total.

For statistics, this disruption is caused due to a points failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.