Points failure: Utrecht-Rotterdam; Utrecht-Den Haag (25 February 2017)
-
Disruption resolved Last update
Between Utrecht Centraal and Rotterdam Centraal the train traffic is fully resumed.
Between Utrecht Centraal and Den Haag Centraal the train traffic is fully resumed. -
Delays decreasing
Between Utrecht Centraal and Rotterdam Centraal the restrictions are resolved.
Between Utrecht Centraal and Den Haag Centraal the restrictions are resolved.
Delays are decreasing.
Service is normal around 6:15 PM hours. -
Update
Between Utrecht Centraal and Rotterdam Centraal fewer intercities are running due to a points failure.
Between Utrecht Centraal and Den Haag Centraal fewer intercities are running due to a points failure.
Service is normal around 6:15 PM hours.Train measures
- Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Utrecht Centraal and Rotterdam Centraal
- Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Utrecht Centraal and Rotterdam Centraal
- Intercity 2000 Den Haag C. - Utrecht C. is cancelled between Den Haag Centraal and Utrecht Centraal
-
Update
Between Utrecht Centraal and Rotterdam Centraal fewer intercities are running due to a points failure.
Between Utrecht Centraal and Den Haag Centraal fewer intercities are running due to a points failure.
This will take until approximately 6:15 PM hours.Train measures
- Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Utrecht Centraal and Rotterdam Centraal
- Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Utrecht Centraal and Rotterdam Centraal
- Intercity 2000 Den Haag C. - Utrecht C. is cancelled between Den Haag Centraal and Utrecht Centraal
-
Update
Between Utrecht Centraal and Rotterdam Centraal fewer intercities are running due to a points failure.
Between Utrecht Centraal and Den Haag Centraal fewer intercities are running due to a points failure.
This will take until approximately 6:15 PM hours. -
Disruption
Between Utrecht Centraal and Rotterdam Centraal fewer intercities are running due to a points failure.
Between Utrecht Centraal and Den Haag Centraal fewer intercities are running due to a points failure.
It is not known yet how long this will take.
More about this disruption
Statistics
This disruption started at 3:46 PM on February 25, 2017 and took 2 hours, 29 minutes in total.
For statistics, this disruption is caused due to a points failure.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.