Stranded train: Schiphol-Lelystad; Lelystad-Zwolle (10 March 2017)
-
Disruption resolved Last update
Between Schiphol Airport and Lelystad Centrum the train traffic is fully resumed.
Between Lelystad Centrum and Zwolle the train traffic is fully resumed. -
Delays decreasing
Between Schiphol Airport and Lelystad Centrum the restrictions are resolved.
Between Lelystad Centrum and Zwolle the restrictions are resolved.
Delays are decreasing.
Service is normal around 12:15 AM hours. -
Update
Between Schiphol Airport and Lelystad Centrum there are fewer trains running due to a stranded train.
Between Lelystad Centrum and Zwolle no trains are running due to a stranded train.
This will take until at least 12:30 AM on Saturday, March 11, 2017.Train measures
- Intercity 700 Den Haag C. - Schiphol Airport - Lelystad C. - Groningen is cancelled between Den Haag Centraal and Zwolle
- Intercity 1800 Den Haag C. - Schiphol Airport - Lelystad C. - Leeuwarden is cancelled between Den Haag Centraal and Zwolle
- Intercity 2400 Lelystad C. - Schiphol Airport - Rotterdam C. - Dordrecht is cancelled between Leiden Centraal and Lelystad Centrum
-
Update
Between Schiphol Airport and Lelystad Centrum there are fewer trains running due to a stranded train.
Between Lelystad Centrum and Zwolle there are fewer trains running due to a stranded train.
This will take until at least 12:30 AM on Saturday, March 11, 2017.Train measures
- Intercity 700 Den Haag C. - Schiphol Airport - Lelystad C. - Groningen is cancelled between Den Haag Centraal and Zwolle
- Intercity 1800 Den Haag C. - Schiphol Airport - Lelystad C. - Leeuwarden is cancelled between Den Haag Centraal and Zwolle
- Intercity 2400 Lelystad C. - Schiphol Airport - Rotterdam C. - Dordrecht is cancelled between Leiden Centraal and Lelystad Centrum
-
Update
Between Schiphol Airport and Lelystad Centrum there are fewer trains running due to a stranded train.
This will take until at least 11:30 PM hours.Train measures
- Intercity 700 Den Haag C. - Schiphol Airport - Lelystad C. - Groningen is cancelled between Den Haag Centraal and Almere Centrum
- Intercity 1800 Den Haag C. - Schiphol Airport - Lelystad C. - Leeuwarden is cancelled between Den Haag Centraal and Almere Centrum
- Intercity 2400 Lelystad C. - Schiphol Airport - Rotterdam C. - Dordrecht is cancelled between Leiden Centraal and Lelystad Centrum
-
Update
Between Schiphol Airport and Lelystad Centrum there are fewer trains running due to a stranded train.
Between Lelystad Centrum and Zwolle there are fewer trains running due to a stranded train.
This will take until at least 11:30 PM hours.Train measures
- Intercity 700 Den Haag C. - Schiphol Airport - Lelystad C. - Groningen is cancelled between Den Haag Centraal and Almere Centrum
- Intercity 1800 Den Haag C. - Schiphol Airport - Lelystad C. - Leeuwarden is cancelled between Den Haag Centraal and Almere Centrum
- Intercity 2400 Lelystad C. - Schiphol Airport - Rotterdam C. - Dordrecht is cancelled between Leiden Centraal and Lelystad Centrum
-
Update
Between Schiphol Airport and Lelystad Centrum there are fewer trains running due to a stranded train.
Between Lelystad Centrum and Zwolle there are fewer trains running due to a stranded train.
This will take until at least 11:30 PM hours. -
Disruption
Between Schiphol Airport and Lelystad Centrum there are fewer trains running due to a stranded train.
Between Lelystad Centrum and Zwolle there are fewer trains running due to a stranded train.
This will take until approximately 11:30 PM hours.
More about this disruption
Statistics
This disruption started at 9:55 PM on March 10, 2017 and took 2 hours, 20 minutes in total.
For statistics, this disruption is caused due to a stranded train.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.