overwegstoring

Level crossing failure: Alphen a/d Rijn-Gouda (18 May 2017)

  1. Disruption resolved Last update

    Between Alphen a/d Rijn and Gouda the train traffic is fully resumed.

    Advice

    Passengers between Alphen a/d Rijn and Gouda travel via Woerden. The extra travel time is between 15 and 30 minutes.

  2. Delays decreasing

    Between Alphen a/d Rijn and Gouda the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 1:00 AM hours.

    Advice

    Passengers between Alphen a/d Rijn and Gouda travel via Woerden. The extra travel time is between 15 and 30 minutes.

  3. Update

    Between Alphen a/d Rijn and Gouda no trains are running due to a level crossing failure.
    This will take until at least 1:30 AM on Friday, May 19, 2017.

    Advice

    Local buses are running between Alphen a/d Rijn, Boskoop, Waddinxveen Noord, Waddinxveen and Gouda.
    Passengers between Alphen a/d Rijn and Gouda travel via Woerden. The extra travel time is between 15 and 30 minutes.

    Train measures

    • Sprinter 8600 Gouda - Alphen a/d Rijn is cancelled between Alphen a/d Rijn and Gouda
  4. Update

    Between Alphen a/d Rijn and Gouda no trains are running due to a level crossing failure.
    This will take until at least 1:30 AM on Friday, May 19, 2017.

    Advice

    Passengers between Alphen a/d Rijn and Gouda travel via Woerden. The extra travel time is between 15 and 30 minutes.

    Train measures

    • Sprinter 8600 Gouda - Alphen a/d Rijn is cancelled between Alphen a/d Rijn and Gouda
  5. Update

    Between Alphen a/d Rijn and Gouda no trains are running due to a level crossing failure.
    It is not known yet how long this will take.

    Advice

    Passengers between Alphen a/d Rijn and Gouda travel via Woerden. The extra travel time is between 15 and 30 minutes.

  6. Disruption

    Between Alphen a/d Rijn and Gouda no trains are running due to a level crossing failure.
    It is not known yet how long this will take.

More about this disruption

Statistics

This disruption started at 10:16 PM on May 18, 2017 and took 2 hours, 44 minutes in total.

For statistics, this disruption is caused due to a level crossing failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by R-net.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights