seinstoring

Signal failure: Groningen-Bad Nieuweschans (23 May 2017)

  1. Disruption resolved Last update

    Between Zuidbroek and Winschoten the train traffic is fully resumed.

  2. Delays decreasing

    Between Zuidbroek and Winschoten the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 7:45 AM hours.

  3. Delays decreasing

    Between Zuidbroek and Winschoten the restrictions are resolved.
    Delays are decreasing.
    The first trains are expected to be running after 7:45 AM hours.

  4. Delays decreasing

    Between Zuidbroek and Winschoten the restrictions are resolved.
    Delays are decreasing.
    The first trains are expected to be running after 7:30 AM hours.

  5. Update

    Between Zuidbroek and Winschoten there are delays and fewer trains are running due to a signal failure.
    The extra travel time may be up to 15 minutes.
    It is not known yet how long this will take.

  6. Disruption

    Between Scheemda and Winschoten there is a service disruption due to a signal failure.
    Updates will follow as more information becomes available.

More about this disruption

Statistics

This disruption started at 6:40 AM on May 23, 2017 and took 1 hour, 5 minutes in total.

For statistics, this disruption is caused due to a signal failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by Arriva.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights