Signal and level crossing failure: Breda-Tilburg (7 June 2017)
-
Disruption resolved Last update
Between Breda and Tilburg the train traffic is fully resumed.
-
Delays decreasing
Between Breda and Tilburg the restrictions are resolved.
Delays are decreasing.
The first trains are expected to be running after 11:45 PM hours. -
Update
Between Breda and Tilburg far fewer trains are running due to a signal and level crossing failure.
It is not known yet how long this will take. -
Disruption
Between Breda and Tilburg there is a service disruption due to a signal and level crossing failure.
Updates will follow as more information becomes available.
More about this disruption
Statistics
This disruption started at 9:07 PM on June 7, 2017 and took 2 hours, 40 minutes in total.
For statistics, this disruption is caused due to a signal and level crossing failure.
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.