wisselstoring

Points failure: Utrecht-Den Haag (20 June 2017)

  1. Disruption resolved Last update

    Between Utrecht Centraal and Den Haag Centraal the train traffic is fully resumed.

  2. Delays decreasing

    Between Utrecht Centraal and Den Haag Centraal the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 11:45 AM hours.

  3. Update

    Between Utrecht Centraal and Rotterdam Centraal fewer intercities are running due to a points failure.
    Between Utrecht Centraal and Den Haag Centraal fewer intercities are running due to a points failure.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 12:00 PM hours.

    Train measures

    • Intercity 2000 Den Haag C. - Utrecht C. is cancelled between Den Haag Centraal and Utrecht Centraal
    • Intercity 2800 Rotterdam C. - Utrecht C. is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Sprinter 6800 Den Haag C. - Gouda Goverwelle is cancelled between Gouda and Gouda Goverwelle
  4. Update

    Between Utrecht Centraal and Rotterdam Centraal fewer intercities are running due to a points failure.
    Between Utrecht Centraal and Den Haag Centraal fewer intercities are running due to a points failure.
    The extra travel time may be up to 30 minutes.
    It is not known yet how long this will take.

    Train measures

    • Intercity 2000 Den Haag C. - Utrecht C. is cancelled between Den Haag Centraal and Utrecht Centraal
    • Intercity 2800 Rotterdam C. - Utrecht C. is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Sprinter 6800 Den Haag C. - Gouda Goverwelle is cancelled between Gouda and Gouda Goverwelle
  5. Update

    Between Utrecht Centraal and Den Haag Centraal fewer intercities are running due to a points failure.
    Between Utrecht Centraal and Rotterdam Centraal fewer intercities are running due to a points failure.
    The extra travel time may be up to 30 minutes.
    It is not known yet how long this will take.

  6. Update

    Between Utrecht Centraal and Den Haag Centraal fewer intercities are running due to a points failure.
    The extra travel time may be up to 30 minutes.
    It is not known yet how long this will take.

  7. Disruption

    Between Utrecht Centraal and Den Haag Centraal fewer intercities are running due to a points failure.
    Between Utrecht Centraal and Rotterdam Centraal fewer intercities are running due to a points failure.
    The extra travel time may be up to 30 minutes.
    It is not known yet how long this will take.

More about this disruption

Statistics

This disruption started at 9:25 AM on June 20, 2017 and took 2 hours, 20 minutes in total.

For statistics, this disruption is caused due to a points failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.