Signal failure: Arnhem-Winterswijk (6 July 2017)
-
Disruption resolved Last update
Between Doetinchem and Winterswijk the train traffic is fully resumed.
-
Delays decreasing
Between Doetinchem and Winterswijk the restrictions are resolved.
Delays are decreasing.
Service is normal around 11:45 AM hours.Advice
Buses are still running between Doetinchem and Winterswijk.
-
Delays decreasing
Between Doetinchem and Winterswijk the restrictions are resolved.
Delays are decreasing.
Service is normal around 11:45 AM hours.Advice
Buses are still running between Doetinchem and Winterswijk.
Passengers between Arnhem Centraal and Winterswijk travel via Zutphen. No extra travel time. -
Delays decreasing
Between Doetinchem and Winterswijk the restrictions are resolved.
Delays are decreasing.
It is not known yet how long this will take.Advice
Buses are still running between Doetinchem and Winterswijk.
Passengers between Arnhem Centraal and Winterswijk travel via Zutphen. No extra travel time. -
Update
Between Doetinchem and Winterswijk no trains are running due to a signal failure.
It is not known yet how long this will take.Advice
Local buses are running between Doetinchem and Winterswijk.
Passengers between Arnhem Centraal and Winterswijk travel via Zutphen. No extra travel time.Train measures
- Stoptrein 30900 Arnhem C. - Winterswijk is cancelled between Doetinchem and Winterswijk
-
Update
Between Doetinchem and Winterswijk no trains are running due to a signal failure.
It is not known yet how long this will take.Advice
Passengers between Arnhem Centraal and Winterswijk travel via Zutphen. No extra travel time.
Train measures
- Stoptrein 30900 Arnhem C. - Winterswijk is cancelled between Doetinchem and Winterswijk
-
Update
Between Doetinchem and Winterswijk no trains are running due to a signal failure.
It is not known yet how long this will take. -
Disruption
Between Doetinchem and Winterswijk there is a service disruption due to a signal failure.
Updates will follow as more information becomes available.
More about this disruption
Statistics
This disruption started at 10:36 AM on July 6, 2017 and took 1 hour, 9 minutes in total.
For statistics, this disruption is caused due to a signal failure.
Operators
This disruption affects trains operated by Arriva and Breng.