wisselstoring

Points failure: Schiphol Airport (16 July 2017)

  1. Disruption resolved Last update

    From and to Schiphol Airport the train traffic is fully resumed.

  2. Delays decreasing

    From and to Schiphol Airport the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 1:00 PM hours.

  3. Update

    From and to Schiphol Airport there are fewer trains running due to a points failure.
    It is not known yet how long this will take.

    Train measures

    • Intercity direct 1000 Amsterdam C. - Schiphol Airport - Rotterdam C. is cancelled between Amsterdam Centraal and Rotterdam Centraal
    • Intercity 2400 Lelystad C. - Schiphol Airport - Rotterdam C. - Dordrecht is cancelled between Duivendrecht and Leiden Centraal
    • Intercity 3100 Schiphol Airport - Utrecht C. - Nijmegen is cancelled between Amsterdam Zuid and Schiphol Airport
  4. Update

    From and to Schiphol Airport there are fewer trains running due to a points failure.
    It is not known yet how long this will take.

    Train measures

    • Intercity direct 1000 Amsterdam C. - Schiphol Airport - Rotterdam C. is cancelled between Amsterdam Centraal and Rotterdam Centraal
    • Intercity 2400 Lelystad C. - Schiphol Airport - Rotterdam C. - Dordrecht is cancelled between Lelystad Centrum and Leiden Centraal
    • Intercity 3100 Schiphol Airport - Utrecht C. - Nijmegen is cancelled between Amsterdam Zuid and Schiphol Airport
  5. Disruption

    From and to Schiphol Airport there are fewer trains running due to a points failure.
    It is not known yet how long this will take.

More about this disruption

Statistics

This disruption started at 12:59 PM on July 16, 2017 and took 0 seconds in total.

For statistics, this disruption is caused due to a points failure.

Operators

This disruption affects trains operated by NS, NS International and Thalys.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights