Problems with the signalling system: Heerlen Roermond Maastricht (19 July 2017)

  1. Disruption resolved Last update

    From and to Heerlen the train traffic is fully resumed.
    From and to Roermond the train traffic is fully resumed.
    From and to Maastricht the train traffic is fully resumed.

  2. Disruption resolved

    From and to Heerlen the train traffic is fully resumed.
    From and to Maastricht the train traffic is fully resumed.
    From and to Roermond the train traffic is fully resumed.

  3. Update

    From and to Heerlen there are delays due to problems with the signalling system.
    From and to Maastricht there are delays due to problems with the signalling system.
    From and to Roermond there are delays due to problems with the signalling system.
    It is not known yet how long this will take.

  4. Disruption

    From and to Maastricht there are delays and fewer trains are running due to problems with the signalling system.
    From and to Heerlen there are delays and fewer trains are running due to problems with the signalling system.
    From and to Roermond there are delays and fewer trains are running due to problems with the signalling system.
    It is not known yet how long this will take.

More about this disruption

Statistics

This disruption started at 8:27 AM on July 19, 2017 and took 7 hours, 1 minute in total.

For statistics, this disruption is caused due to problems with the signalling system.

Operators

This disruption affects trains operated by NS, Arriva, NMBS and Deutsche Bahn.