Points failure: Den Haag-Gouda Goverwelle (7 September 2017)
-
Disruption resolved Last update
Between Gouda Goverwelle and Den Haag Centraal the train traffic is fully resumed.
Train measures
- Sprinter 6800 Den Haag C. - Gouda Goverwelle is cancelled between Gouda Goverwelle and Den Haag Centraal
-
Update
Between Gouda Goverwelle and Den Haag Centraal fewer Sprinter trains are running due to a points failure.
The extra travel time may be up to 15 minutes.
Service is normal around 9:00 PM hours.Train measures
- Sprinter 6800 Den Haag C. - Gouda Goverwelle is cancelled between Gouda Goverwelle and Den Haag Centraal
-
Update
Between Gouda and Den Haag Centraal fewer Sprinter trains are running due to a points failure.
The extra travel time may be up to 15 minutes.
Service is normal around 9:00 PM hours.Train measures
- Sprinter 6800 Den Haag C. - Gouda Goverwelle is cancelled between Gouda Goverwelle and Den Haag Centraal
-
Update
Between Gouda and Den Haag Centraal fewer Sprinter trains are running due to a points failure.
The extra travel time may be up to 15 minutes.
This will take the rest of the day.Train measures
- Sprinter 6800 Den Haag C. - Gouda Goverwelle is cancelled between Gouda Goverwelle and Den Haag Centraal
-
Update
Between Gouda and Den Haag Centraal far fewer trains are running due to a points failure.
The extra travel time may be up to 60 minutes.
This will take until approximately 5:00 PM hours.Train measures
- Intercity 1700 Den Haag C. - Amersfoort - Hengelo - Enschede is cancelled between Den Haag Centraal and Utrecht Centraal
- Intercity 2000 Den Haag C. - Utrecht C. is cancelled between Den Haag Centraal and Utrecht Centraal
- Sprinter 6800 Den Haag C. - Gouda Goverwelle is cancelled between Gouda Goverwelle and Den Haag Centraal
- Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Den Haag Centraal and Utrecht Centraal
-
Update
Between Gouda and Den Haag Centraal far fewer trains are running due to a points failure.
The extra travel time may be up to 60 minutes.
This will take until approximately 3:30 PM hours.Train measures
- Intercity 1700 Den Haag C. - Amersfoort - Hengelo - Enschede is cancelled between Den Haag Centraal and Utrecht Centraal
- Intercity 2000 Den Haag C. - Utrecht C. is cancelled between Den Haag Centraal and Utrecht Centraal
- Sprinter 6800 Den Haag C. - Gouda Goverwelle is cancelled between Gouda Goverwelle and Den Haag Centraal
- Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Den Haag Centraal and Utrecht Centraal
-
Update
Between Gouda and Den Haag Centraal far fewer trains are running due to a points failure.
This will take until approximately 3:30 PM hours.Train measures
- Intercity 1700 Den Haag C. - Amersfoort - Hengelo - Enschede is cancelled between Den Haag Centraal and Utrecht Centraal
- Intercity 2000 Den Haag C. - Utrecht C. is cancelled between Den Haag Centraal and Utrecht Centraal
- Sprinter 6800 Den Haag C. - Gouda Goverwelle is cancelled between Gouda Goverwelle and Den Haag Centraal
- Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Den Haag Centraal and Utrecht Centraal
-
Update
Between Gouda and Den Haag Centraal far fewer trains are running due to a points failure.
This will take until approximately 3:30 PM hours. -
Update
Between Gouda and Den Haag Centraal far fewer trains are running due to a points failure.
It is not known yet how long this will take. -
Disruption
Between Gouda and Den Haag Centraal there are fewer trains running due to a points failure.
It is not known yet how long this will take.
More about this disruption
Statistics
This disruption started at 1:00 PM on September 7, 2017 and took 8 hours in total.
For statistics, this disruption is caused due to a points failure.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.