Problems with the rolling stock: Almelo-Hardenberg (12 September 2017)

  1. Disruption resolved Last update

    Between Almelo and Mariënberg the train traffic is fully resumed.

    Advice

    Buses are running between Almelo, Vriezenveen, Daarlerveen, Vroomshoop, Mariënberg and Hardenberg.

  2. Update

    Between Almelo and Mariënberg there are fewer trains running due to problems with the rolling stock.
    This will take until approximately 9:30 AM hours.

    Advice

    Buses are running between Almelo, Vriezenveen, Daarlerveen, Vroomshoop, Mariënberg and Hardenberg.

  3. Update

    Between Almelo and Mariënberg there are fewer trains running due to problems with the rolling stock.
    This will take until approximately 9:30 AM hours.

  4. Update

    Between Almelo and Mariënberg there are fewer trains running due to problems with the rolling stock.
    It is not known yet how long this will take.

  5. Disruption

    Between Almelo and Mariënberg no trains are running due to problems with the rolling stock.
    It is not known yet how long this will take.

More about this disruption

Statistics

This disruption started at 5:56 AM on September 12, 2017 and took 3 hours, 37 minutes in total.

For statistics, this disruption is caused due to problems with the rolling stock.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by Arriva.

Got delayed due to this disruption? You may be reimbursed.