Level crossing failure: Deventer-Almelo (15 September 2017)
-
Disruption resolved Last update
Between Deventer and Rijssen the train traffic is fully resumed.
-
Delays decreasing
Between Deventer and Rijssen the restrictions are resolved.
Delays are decreasing.
Service is normal around 12:45 AM hours. -
Update
Between Deventer and Rijssen there are delays due to a level crossing failure.
The extra travel time may be up to 30 minutes.
It is not known yet how long this will take. -
Delays decreasing
Between Deventer and Rijssen the restrictions are resolved.
Delays are decreasing.
Service is normal around 12:00 AM on Saturday, September 16, 2017. -
Disruption
Between Deventer and Rijssen there are delays due to a level crossing failure.
The extra travel time may be up to 15 minutes.
This will take until approximately 1:30 AM on Saturday, September 16, 2017. -
Update
Between Deventer and Rijssen there is a service disruption due to a level crossing failure.
Updates will follow as more information becomes available.
More about this disruption
Statistics
This disruption started at 10:57 PM on September 15, 2017 and took 1 hour, 45 minutes in total.
For statistics, this disruption is caused due to a level crossing failure.
Operators
This disruption affects trains operated by NS and NS International.
Got delayed due to this disruption? You may be reimbursed.