overwegstoring

Level crossing failure: Eindhoven-Deurne (25 September 2017)

  1. Disruption resolved Last update

    Between Eindhoven and Deurne the train traffic is fully resumed.

  2. Delays decreasing

    Between Eindhoven and Deurne the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 8:30 PM hours.

  3. Delays decreasing

    Between Eindhoven and Deurne the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 9:30 PM hours.

  4. Update

    Between Eindhoven and Deurne no Sprinters are running due to a level crossing failure.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 9:15 PM hours.

    Advice

    Local buses are running between Helmond Brandevoort, Helmond 't Hout and Helmond.

    Train measures

    • Sprinter 9600 Deurne - Eindhoven - 's-Hertogenbosch is cancelled between Eindhoven and Deurne
    • Intercity 13500 Eindhoven - Venlo will make an extra stop at Helmond Brouwhuis
  5. Update

    Between Eindhoven and Deurne no Sprinters are running due to a level crossing failure.
    The extra travel time may be up to 60 minutes.
    This will take until approximately 9:15 PM hours.

    Train measures

    • Sprinter 9600 Deurne - Eindhoven - 's-Hertogenbosch is cancelled between Eindhoven and Deurne
    • Intercity 13500 Eindhoven - Venlo will make an extra stop at Helmond Brouwhuis
  6. Update

    Between Eindhoven and Deurne no Sprinters are running due to a level crossing failure.
    The extra travel time may be up to 60 minutes.
    It is not known yet how long this will take.

    Train measures

    • Sprinter 9600 Deurne - Eindhoven - 's-Hertogenbosch is cancelled between Eindhoven and Deurne
    • Intercity 13500 Eindhoven - Venlo will make an extra stop at Helmond Brouwhuis
  7. Update

    Between Eindhoven and Deurne no Sprinters are running due to a level crossing failure.
    The extra travel time may be up to 60 minutes.
    It is not known yet how long this will take.

  8. Disruption

    Between Eindhoven and Deurne there is a service disruption due to a level crossing failure.
    Updates will follow as more information becomes available.

  9. Update

    Between Eindhoven and Deurne there is a service disruption due to a signal failure.
    Updates will follow as more information becomes available.

More about this disruption

Statistics

This disruption started at 6:40 PM on September 25, 2017 and took 1 hour, 49 minutes in total.

For statistics, this disruption is caused due to a level crossing failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights