Points failure: Eindhoven-Roermond (27 September 2017)
-
Disruption resolved Last update
Between Weert and Roermond the train traffic is fully resumed.
-
Delays decreasing
Between Weert and Roermond the restrictions are resolved.
Delays are decreasing.
Service is normal around 1:30 PM hours. -
Update
Between Weert and Roermond no trains are running due to a points failure.
This will take until approximately 1:30 PM hours.Advice
Buses are still running between Weert and Roermond.
Train measures
- Intercity 800 Alkmaar - Utrecht C. - Eindhoven - Maastricht is cancelled between Weert and Roermond
- Intercity 3500 Schiphol Airport - Utrecht C. - Eindhoven - Heerlen is cancelled between Weert and Roermond
-
Update
Between Weert and Roermond no trains are running due to a points failure.
Service is normal around 1:30 PM hours.Advice
Buses are running between Weert and Roermond.
Train measures
- Intercity 800 Alkmaar - Utrecht C. - Eindhoven - Maastricht is cancelled between Weert and Roermond
- Intercity 3500 Schiphol Airport - Utrecht C. - Eindhoven - Heerlen is cancelled between Weert and Roermond
-
Update
Between Weert and Roermond no trains are running due to a points failure.
It is not known yet how long this will take.Advice
Buses are running between Weert and Roermond.
Train measures
- Intercity 800 Alkmaar - Utrecht C. - Eindhoven - Maastricht is cancelled between Weert and Roermond
- Intercity 3500 Schiphol Airport - Utrecht C. - Eindhoven - Heerlen is cancelled between Weert and Roermond
-
Update
Between Weert and Roermond no trains are running due to a points failure.
This will take until approximately 12:45 PM hours.Advice
Buses are running between Weert and Roermond.
Train measures
- Intercity 800 Alkmaar - Utrecht C. - Eindhoven - Maastricht is cancelled between Weert and Roermond
- Intercity 3500 Schiphol Airport - Utrecht C. - Eindhoven - Heerlen is cancelled between Weert and Roermond
-
Update
Between Weert and Roermond no trains are running due to a points failure.
It is not known yet how long this will take.Advice
Buses are running between Weert and Roermond.
Train measures
- Intercity 800 Alkmaar - Utrecht C. - Eindhoven - Maastricht is cancelled between Weert and Roermond
- Intercity 3500 Schiphol Airport - Utrecht C. - Eindhoven - Heerlen is cancelled between Weert and Roermond
-
Update
Between Weert and Roermond no trains are running due to a points failure.
This will take until approximately 11:00 AM hours.Advice
Buses are running between Weert and Roermond.
Train measures
- Intercity 800 Alkmaar - Utrecht C. - Eindhoven - Maastricht is cancelled between Weert and Roermond
- Intercity 3500 Schiphol Airport - Utrecht C. - Eindhoven - Heerlen is cancelled between Weert and Roermond
-
Update
Between Weert and Roermond no trains are running due to a points failure.
It is not known yet how long this will take.Advice
Buses are running between Weert and Roermond.
Train measures
- Intercity 800 Alkmaar - Utrecht C. - Eindhoven - Maastricht is cancelled between Weert and Roermond
- Intercity 3500 Schiphol Airport - Utrecht C. - Eindhoven - Heerlen is cancelled between Weert and Roermond
-
Update
Between Weert and Roermond no trains are running due to a points failure.
It is not known yet how long this will take.Train measures
- Intercity 800 Alkmaar - Utrecht C. - Eindhoven - Maastricht is cancelled between Weert and Roermond
- Intercity 3500 Schiphol Airport - Utrecht C. - Eindhoven - Heerlen is cancelled between Weert and Roermond
-
Update
Between Weert and Roermond no trains are running due to a points failure.
Updates will follow as more information becomes available.Train measures
- Intercity 800 Alkmaar - Utrecht C. - Eindhoven - Maastricht is cancelled between Weert and Roermond
- Intercity 3500 Schiphol Airport - Utrecht C. - Eindhoven - Heerlen is cancelled between Weert and Roermond
-
Disruption
Between Weert and Roermond there is a service disruption due to a points failure.
Updates will follow as more information becomes available.
More about this disruption
Statistics
This disruption started at 8:35 AM on September 27, 2017 and took 4 hours, 50 minutes in total.
For statistics, this disruption is caused due to a points failure.
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.