wisselstoring

Points failure: Roosendaal-Vlissingen (24 November 2017)

  1. Disruption resolved Last update

    Between Roosendaal and Bergen op Zoom the train traffic is fully resumed.

  2. Delays decreasing

    Between Roosendaal and Bergen op Zoom the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 2:15 PM hours.

  3. Update

    Between Roosendaal and Bergen op Zoom no trains are running due to a points failure.
    The extra travel time may be up to 15 minutes.
    It is not known yet how long this will take.

    Advice

    Buses are running between Roosendaal and Bergen op Zoom.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Roosendaal and Bergen op Zoom
  4. Update

    Between Roosendaal and Bergen op Zoom no trains are running due to a points failure.
    The extra travel time may be up to 15 minutes.
    Service is normal around 2:15 PM hours.

    Advice

    Buses are running between Roosendaal and Bergen op Zoom.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Roosendaal and Bergen op Zoom
  5. Update

    Between Roosendaal and Bergen op Zoom no trains are running due to a points failure.
    The extra travel time may be up to 15 minutes.
    This will take until approximately 2:30 PM hours.

    Advice

    Buses are running between Roosendaal and Bergen op Zoom.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Roosendaal and Bergen op Zoom
  6. Update

    Between Roosendaal and Bergen op Zoom no trains are running due to a points failure.
    The extra travel time may be up to 60 minutes.
    This will take until approximately 2:30 PM hours.

    Advice

    Buses are running between Roosendaal and Bergen op Zoom.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Roosendaal and Bergen op Zoom
  7. Update

    Between Roosendaal and Bergen op Zoom no trains are running due to a points failure.
    The extra travel time may be up to 60 minutes.
    This will take until approximately 2:30 PM hours.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Roosendaal and Bergen op Zoom
  8. Update

    Between Roosendaal and Bergen op Zoom no trains are running due to a points failure.
    The extra travel time may be up to 60 minutes.
    This will take until approximately 2:30 PM hours.

  9. Update

    Between Roosendaal and Bergen op Zoom no trains are running due to a points failure.
    The extra travel time may be up to 60 minutes.
    It is not known yet how long this will take.

  10. Disruption

    Between Roosendaal and Bergen op Zoom there is a service disruption due to a points failure.
    Updates will follow as more information becomes available.

More about this disruption

Statistics

This disruption started at 11:45 AM on November 24, 2017 and took 2 hours, 28 minutes in total.

For statistics, this disruption is caused due to a points failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.