wisselstoring

Points failure: Utrecht-Den Haag (11 December 2017)

  1. Disruption resolved Last update

    Between Utrecht Centraal and Den Haag Centraal the train traffic is fully resumed.

  2. Update

    Between Utrecht Centraal and Den Haag Centraal no intercities are running due to a points failure.
    The extra travel time is between 30 and 60 minutes.
    This will take until approximately 9:30 PM hours.

  3. Update

    Between Utrecht Centraal and Den Haag Centraal no intercities are running due to a points failure.
    The extra travel time is between 30 and 60 minutes.
    This will take the rest of the day.

  4. Update

    Between Utrecht Centraal and Den Haag Centraal fewer intercities are running due to a points failure.
    The extra travel time is between 30 and 60 minutes.
    This will take the rest of the day.

  5. Disruption

    Between Utrecht Centraal and Den Haag Centraal no intercities are running due to a points failure.
    This will take the rest of the day.

More about this disruption

Statistics

This disruption started at 8:08 AM on December 11, 2017 and took 12 hours, 54 minutes in total.

For statistics, this disruption is caused due to a points failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.