Weather circumstances: Amersfoort-Barneveld (11 December 2017)

  1. Disruption resolved Last update

    Between Amersfoort and Barneveld Zuid the train traffic is fully resumed.

  2. Delays decreasing

    Between Amersfoort and Barneveld Zuid the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 9:00 PM hours.

  3. Update

    Between Amersfoort and Barneveld Zuid there are fewer local trains running due to weather conditions.
    The extra travel time may be up to 15 minutes.
    Service is normal around 9:00 PM hours.

  4. Update

    Between Amersfoort and Barneveld Zuid there are fewer local trains running due to weather conditions.
    The extra travel time may be up to 15 minutes.
    This will take until approximately 8:00 PM hours.

  5. Update

    Between Amersfoort and Barneveld Zuid there are fewer local trains running due to weather conditions.
    The extra travel time is about 15 minutes.
    This will take until approximately 8:00 PM hours.

  6. Disruption

    Between Amersfoort and Barneveld Zuid there are fewer local trains running due to weather conditions.
    The extra travel time is about 15 minutes.
    It is not known yet how long this will take.

More about this disruption

Statistics

This disruption started at 1:08 PM on December 11, 2017 and took 7 hours, 39 minutes in total.

For statistics, this disruption is caused due to weather circumstances.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by Connexxion.

Got delayed due to this disruption? You may be reimbursed.