defect spoor

Defective railway track: Amsterdam-Utrecht (12 January 2018)

  1. Disruption resolved Last update

    Between Amsterdam Centraal and Utrecht Centraal the train traffic is fully resumed.

  2. Delays decreasing

    Between Amsterdam Centraal and Utrecht Centraal the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 11:30 AM hours.

  3. Update

    Between Amsterdam Centraal and Utrecht Centraal fewer intercities are running due to a defective railway track.
    The extra travel time is about 15 minutes.
    This will take until approximately 11:30 AM hours.

    Train measures

    • Intercity 3900 Amsterdam C. - Utrecht C. - Eindhoven is cancelled between Amsterdam Centraal and Eindhoven
  4. Update

    Between Amsterdam Centraal and Utrecht Centraal fewer intercities are running due to a defective railway track.
    The extra travel time is about 15 minutes.
    This will take until approximately 10:15 AM hours.

    Train measures

    • Intercity 3900 Amsterdam C. - Utrecht C. - Eindhoven is cancelled between Amsterdam Centraal and Eindhoven
  5. Update

    Between Amsterdam Centraal and Utrecht Centraal fewer intercities are running due to a defective railway track.
    The extra travel time is about 15 minutes.
    Service is normal around 10:15 AM hours.

    Train measures

    • Intercity 3900 Amsterdam C. - Utrecht C. - Eindhoven is cancelled between Amsterdam Centraal and Eindhoven
  6. Update

    Between Amsterdam Centraal and Utrecht Centraal fewer intercities are running due to a defective railway track.
    The extra travel time is about 15 minutes.
    This will take until approximately 12:00 PM hours.

    Train measures

    • Intercity 3900 Amsterdam C. - Utrecht C. - Eindhoven is cancelled between Amsterdam Centraal and Eindhoven
  7. Disruption

    Between Amsterdam Centraal and Utrecht Centraal fewer intercities are running due to a defective railway track.
    The extra travel time is about 15 minutes.
    It is not known yet how long this will take.

More about this disruption

Statistics

This disruption started at 6:14 AM on January 12, 2018 and took 5 hours, 5 minutes in total.

For statistics, this disruption is caused due to a defective railway track.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS and NS International.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights