Points failure: Den Haag-Gouda Goverwelle (12 February 2018)
-
Disruption resolved Last update
Between Den Haag Centraal and Gouda Goverwelle the train traffic is fully resumed.
-
Delays decreasing
Between Den Haag Centraal and Gouda Goverwelle the restrictions are resolved.
Delays are decreasing.
Service is normal around 11:00 AM hours. -
Update
Between Den Haag Centraal and Gouda Goverwelle fewer Sprinter trains are running due to a points failure.
The extra travel time may be up to 15 minutes.
Service is normal around 11:00 AM hours.Train measures
- Sprinter 6800 Den Haag C. - Gouda Goverwelle is cancelled between Den Haag Centraal and Gouda Goverwelle
-
Update
Between Den Haag Centraal and Gouda Goverwelle fewer Sprinter trains are running due to a points failure.
The extra travel time may be up to 15 minutes.
This will take until approximately 11:30 AM hours.Train measures
- Sprinter 6800 Den Haag C. - Gouda Goverwelle is cancelled between Den Haag Centraal and Gouda Goverwelle
-
Update
Between Den Haag Centraal and Gouda Goverwelle fewer Sprinter trains are running due to a points failure.
The extra travel time may be up to 15 minutes.
This will take until approximately 10:15 AM hours.Train measures
- Sprinter 6800 Den Haag C. - Gouda Goverwelle is cancelled between Den Haag Centraal and Gouda Goverwelle
-
Disruption
Between Den Haag Centraal and Gouda Goverwelle fewer Sprinter trains are running due to a points failure.
The extra travel time may be up to 15 minutes.
It is not known yet how long this will take.Train measures
- Sprinter 6800 Den Haag C. - Gouda Goverwelle is cancelled between Den Haag Centraal and Gouda Goverwelle
More about this disruption
Statistics
This disruption started at 8:22 AM on February 12, 2018 and took 2 hours, 35 minutes in total.
For statistics, this disruption is caused due to a points failure.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.