wisselstoring

Points failure: Eindhoven-Venlo; Nijmegen-Venlo (27 February 2018)

  1. Disruption resolved Last update

    Between Blerick and Venlo the train traffic is fully resumed.

  2. Delays decreasing

    Between Blerick and Venlo the restrictions are resolved.
    Delays are decreasing.
    It is not known yet how long this will take.

  3. Disruption

    Between Blerick and Venlo there are fewer trains running due to a points failure.
    It is not known yet how long this will take.

More about this disruption

Statistics

This disruption started at 9:32 AM on February 27, 2018 and took 1 hour, 27 minutes in total.

For statistics, this disruption is caused due to a points failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS and Arriva.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights