Damaged overhead wires: Dordrecht-Breda (23 March 2018)

  1. Disruption resolved Last update

    Between Dordrecht and Breda the train traffic is fully resumed.

  2. Update

    Between Dordrecht and Breda no intercities are running due to damaged overhead wires.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 5:30 PM hours.

    Train measures

    • Intercity 2300 Dordrecht - Breda is cancelled between Dordrecht and Breda
  3. Update

    Between Dordrecht and Breda no intercities are running due to damaged overhead wires.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 4:30 PM hours.

    Train measures

    • Intercity 2300 Dordrecht - Breda is cancelled between Dordrecht and Breda
  4. Update

    Between Dordrecht and Breda no intercities are running due to damaged overhead wires.
    The extra travel time may be up to 30 minutes.
    It is not known yet how long this will take.

  5. Disruption

    Between Dordrecht and Breda no intercities are running due to damaged overhead wires.
    The extra travel time is more than 30 minutes.
    It is not known yet how long this will take.

More about this disruption

Statistics

This disruption started at 1:46 PM on March 23, 2018 and took 2 hours, 53 minutes in total.

For statistics, this disruption is caused due to damaged overhead wires.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.