wisselstoring

Points failure: Utrecht-Leiden (13 June 2018)

  1. Disruption resolved Last update

    Between Bodegraven and Leiden Lammenschans the train traffic is fully resumed.

  2. Delays decreasing

    Between Bodegraven and Leiden Lammenschans the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 6:30 PM hours.

  3. Delays decreasing

    Between Bodegraven and Leiden Lammenschans the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 6:30 PM hours.

    Advice

    Local buses are still running between Bodegraven, Alphen a/d Rijn and Leiden Lammenschans.

  4. Update

    Between Bodegraven and Leiden Lammenschans no trains are running due to a points failure.
    This will take until approximately 6:30 PM hours.

    Advice

    Local buses are running between Bodegraven, Alphen a/d Rijn and Leiden Lammenschans.

    Train measures

    • Intercity 8800 Leiden C. - Utrecht C. is cancelled between Bodegraven and Leiden Lammenschans
  5. Update

    Between Bodegraven and Leiden Lammenschans no trains are running due to a points failure.
    This will take until approximately 6:30 PM hours.

    Train measures

    • Intercity 8800 Leiden C. - Utrecht C. is cancelled between Bodegraven and Leiden Lammenschans
  6. Disruption

    Between Bodegraven and Leiden Lammenschans no trains are running due to a points failure.
    It is not known yet how long this will take.

    Train measures

    • Intercity 8800 Leiden C. - Utrecht C. is cancelled between Bodegraven and Leiden Lammenschans

More about this disruption

Statistics

This disruption started at 4:03 PM on June 13, 2018 and took 2 hours, 21 minutes in total.

For statistics, this disruption is caused due to a points failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.