overwegstoring

Level crossing failure: Groningen-Bad Nieuweschans (23 June 2018)

  1. Disruption resolved Last update

    Between Winschoten and Bad Nieuweschans the train traffic is fully resumed.

  2. Delays decreasing

    Between Winschoten and Bad Nieuweschans the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 9:30 PM hours.

  3. Update

    Between Winschoten and Bad Nieuweschans no trains are running due to a level crossing failure.
    The extra travel time may be up to 60 minutes.
    This will take until approximately 9:30 PM hours.

    Train measures

    • Stoptrein 37500 Groningen - Winschoten - Bad Nieuweschans is cancelled between Zuidbroek and Bad Nieuweschans
  4. Update

    Between Winschoten and Bad Nieuweschans no trains are running due to a level crossing failure.
    The extra travel time may be up to 60 minutes.
    This will take until at least 9:30 PM hours.

    Train measures

    • Stoptrein 37500 Groningen - Winschoten - Bad Nieuweschans is cancelled between Zuidbroek and Bad Nieuweschans
  5. Disruption

    Between Winschoten and Bad Nieuweschans no trains are running due to a level crossing failure.
    The extra travel time may be up to 60 minutes.
    It is not known yet how long this will take.

    Train measures

    • Stoptrein 37500 Groningen - Winschoten - Bad Nieuweschans is cancelled between Zuidbroek and Bad Nieuweschans
  6. Update

    Between Winschoten and Bad Nieuweschans there is a service disruption due to a level crossing failure.
    Updates will follow as more information becomes available.

More about this disruption

Statistics

This disruption started at 7:45 PM on June 23, 2018 and took 1 hour, 43 minutes in total.

For statistics, this disruption is caused due to a level crossing failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by Arriva.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights