Signal and level crossing failure: Alkmaar-Den Helder (25 June 2018)
-
Disruption resolved Last update
Between Schagen and Anna Paulowna the train traffic is fully resumed.
-
Delays decreasing
Between Schagen and Anna Paulowna the restrictions are resolved.
Delays are decreasing.
Service is normal around 11:45 AM hours.Advice
Local buses are also running between Anna Paulowna and Schagen.
Train measures
- Intercity 3000 Den Helder - Amsterdam C. - Utrecht C. - Nijmegen is cancelled between Schagen and Anna Paulowna
-
Update
Between Schagen and Anna Paulowna no trains are running due to a signal and level crossing failure.
The extra travel time may be up to 60 minutes.
This will take until approximately 12:30 PM hours.Advice
Local buses are running between Anna Paulowna and Schagen.
Train measures
- Intercity 3000 Den Helder - Amsterdam C. - Utrecht C. - Nijmegen is cancelled between Schagen and Anna Paulowna
-
Update
Between Schagen and Anna Paulowna no trains are running due to a signal and level crossing failure.
The extra travel time may be up to 60 minutes.
This will take until approximately 12:30 PM hours.Train measures
- Intercity 3000 Den Helder - Amsterdam C. - Utrecht C. - Nijmegen is cancelled between Schagen and Anna Paulowna
-
Update
Between Schagen and Anna Paulowna no trains are running due to a signal and level crossing failure.
The extra travel time may be up to 60 minutes.
This will take until approximately 10:30 AM hours.Train measures
- Intercity 3000 Den Helder - Amsterdam C. - Utrecht C. - Nijmegen is cancelled between Schagen and Anna Paulowna
-
Update
Between Schagen and Anna Paulowna no trains are running due to a signal and level crossing failure.
The extra travel time may be up to 60 minutes.
It is not known yet how long this will take.Train measures
- Intercity 3000 Den Helder - Amsterdam C. - Utrecht C. - Nijmegen is cancelled between Schagen and Anna Paulowna
-
Update
Between Schagen and Anna Paulowna no trains are running due to a signal and level crossing failure.
The extra travel time may be up to 60 minutes.
It is not known yet how long this will take. -
Update
Between Schagen and Anna Paulowna there is a service disruption due to a signal and level crossing failure.
It is not known yet how long this will take. -
Disruption
Between Schagen and Anna Paulowna there is a service disruption due to a broken down train.
It is not known yet how long this will take.
More about this disruption
Statistics
This disruption started at 9:02 AM on June 25, 2018 and took 2 hours, 39 minutes in total.
For statistics, this disruption is caused due to a signal and level crossing failure.
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.