Signalling and points failure: Utrecht-Leiden (23 July 2018)
-
Disruption resolved Last update
Between Bodegraven and Alphen a/d Rijn the train traffic is fully resumed.
-
Delays decreasing
Between Bodegraven and Alphen a/d Rijn the restrictions are resolved.
Delays are decreasing.
Service is normal around 6:45 PM hours. -
Update
Between Bodegraven and Alphen a/d Rijn no trains are running due to a signalling and points failure.
This will take until approximately 7:00 PM hours.Advice
Local buses are running between Bodegraven and Alphen a/d Rijn.
Train measures
- Intercity 8800 Leiden C. - Utrecht C. is cancelled between Alphen a/d Rijn and Bodegraven
-
Update
Between Bodegraven and Alphen a/d Rijn no trains are running due to a signalling and points failure.
This will take until approximately 6:30 PM hours.Advice
Local buses are running between Bodegraven and Alphen a/d Rijn.
Train measures
- Intercity 8800 Leiden C. - Utrecht C. is cancelled between Alphen a/d Rijn and Bodegraven
-
Update
Between Bodegraven and Alphen a/d Rijn no trains are running due to a signalling and points failure.
This will take until approximately 6:00 PM hours.Advice
Local buses are running between Bodegraven and Alphen a/d Rijn.
Train measures
- Intercity 8800 Leiden C. - Utrecht C. is cancelled between Alphen a/d Rijn and Bodegraven
-
Update
Between Bodegraven and Alphen a/d Rijn no trains are running due to a signalling and points failure.
This will take until approximately 5:15 PM hours.Advice
Local buses are running between Bodegraven and Alphen a/d Rijn.
Train measures
- Intercity 8800 Leiden C. - Utrecht C. is cancelled between Alphen a/d Rijn and Bodegraven
-
Update
Between Bodegraven and Alphen a/d Rijn no trains are running due to a signalling and points failure.
This will take until approximately 3:30 PM hours.Advice
Local buses are running between Bodegraven and Alphen a/d Rijn.
Train measures
- Intercity 8800 Leiden C. - Utrecht C. is cancelled between Alphen a/d Rijn and Bodegraven
-
Update
Between Bodegraven and Alphen a/d Rijn no trains are running due to a signalling and points failure.
This will take until approximately 3:30 PM hours.Train measures
- Intercity 8800 Leiden C. - Utrecht C. is cancelled between Alphen a/d Rijn and Bodegraven
-
Update
Between Bodegraven and Alphen a/d Rijn no trains are running due to a signalling and points failure.
It is not known yet how long this will take.Train measures
- Intercity 8800 Leiden C. - Utrecht C. is cancelled between Alphen a/d Rijn and Bodegraven
-
Disruption
Between Alphen a/d Rijn and Bodegraven there is a service disruption due to a signalling and points failure.
Updates will follow as more information becomes available.
More about this disruption
Statistics
This disruption started at 1:41 PM on July 23, 2018 and took 5 hours, 3 minutes in total.
For statistics, this disruption is caused due to a signalling and points failure.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.