Storm damage: Amsterdam-Hannover-Berlin (10 August 2018)
-
Disruption resolved Last update
Between Bad Bentheim and Osnabrück Hbf the train traffic is fully resumed.
-
Update
Between Bad Bentheim and Osnabrück Hbf buses are running instead of trains due to storm damage.
It is not known yet how long this will take. -
Disruption
Between Bad Bentheim and Osnabrück Hbf buses are running instead of trains due to weather conditions.
It is not known yet how long this will take.
More about this disruption
Statistics
This disruption started at 9:04 AM on August 10, 2018 and took 1 hour, 50 minutes in total.
For statistics, this disruption is caused due to storm damage.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS International, Deutsche Bahn, eurobahn and Blauwnet.