defecte bovenleiding

Damaged overhead wires: Dordrecht-Breda (13 August 2018)

  1. Disruption resolved Last update

    Between Breda and Dordrecht the train traffic is fully resumed.

  2. Delays decreasing

    Between Breda and Dordrecht the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 5:30 PM hours.

  3. Update

    Between Breda and Dordrecht the train schedule is modified due to damaged overhead wires.
    The extra travel time may be up to 15 minutes.
    This will take until approximately 6:00 PM hours.

    Train measures

    • Intercity direct 900 Amsterdam C. - Schiphol Airport - Rotterdam C. - Breda is cancelled between Breda and Rotterdam Centraal
    • Intercity 2300 Dordrecht - Breda is cancelled between Breda and Dordrecht
    • Sprinter 6600 Dordrecht - Breda - 's-Hertogenbosch is cancelled between Breda and Dordrecht
  4. Update

    Between Breda and Dordrecht the train schedule is modified due to damaged overhead wires.
    The extra travel time may be up to 15 minutes.
    This will take until approximately 6:30 PM hours.

    Train measures

    • Intercity direct 900 Amsterdam C. - Schiphol Airport - Rotterdam C. - Breda is cancelled between Breda and Rotterdam Centraal
    • Intercity 2300 Dordrecht - Breda is cancelled between Breda and Dordrecht
    • Sprinter 6600 Dordrecht - Breda - 's-Hertogenbosch is cancelled between Breda and Dordrecht
  5. Update

    Between Breda and Dordrecht the train schedule is modified due to damaged overhead wires.
    The extra travel time may be up to 15 minutes.
    This will take until approximately 6:30 PM hours.

    Train measures

    • Intercity direct 900 Amsterdam C. - Schiphol Airport - Rotterdam C. - Breda is cancelled between Breda and Rotterdam Centraal
    • Intercity 2300 Dordrecht - Breda is cancelled between Breda and Dordrecht
    • Sprinter 5000 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Rotterdam Centraal and Den Haag Centraal
    • Sprinter 6600 Dordrecht - Breda - 's-Hertogenbosch is cancelled between Breda and Dordrecht
  6. Update

    Between Breda and Dordrecht the train schedule is modified due to damaged overhead wires.
    The extra travel time is between {time_min} minutes.
    This will take until approximately 6:30 PM hours.

    Train measures

    • Intercity direct 900 Amsterdam C. - Schiphol Airport - Rotterdam C. - Breda is cancelled between Breda and Rotterdam Centraal
    • Intercity 2300 Dordrecht - Breda is cancelled between Breda and Dordrecht
    • Sprinter 5000 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Rotterdam Centraal and Den Haag Centraal
    • Sprinter 6600 Dordrecht - Breda - 's-Hertogenbosch is cancelled between Breda and Dordrecht
  7. Disruption

    Between Breda and Dordrecht the train schedule is modified due to damaged overhead wires.
    The extra travel time is between {time_min} minutes.
    It is not known yet how long this will take.

More about this disruption

Statistics

This disruption started at 3:54 PM on August 13, 2018 and took 1 hour, 24 minutes in total.

For statistics, this disruption is caused due to damaged overhead wires.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights