Defective railway track: Groningen-Leer (28 September 2018)
-
Disruption resolved Last update
Between Winschoten and Weener the train traffic is fully resumed.
-
Delays decreasing
Between Winschoten and Weener the restrictions are resolved.
Delays are decreasing.
Service is normal around 6:30 PM hours. -
Delays decreasing
Between Winschoten and Weener the restrictions are resolved.
Delays are decreasing.
The first trains are expected to be running after 6:30 PM hours. -
Delays decreasing
Between Winschoten and Weener the restrictions are resolved.
Delays are decreasing.
The first trains are expected to be running after 6:45 PM hours. -
Update
Between Winschoten and Weener no trains are running due to a defective railway track.
The extra travel time is more than 60 minutes.
The first trains are expected to be running after 6:30 PM hours. -
Update
Between Winschoten and Weener no trains are running due to a defective railway track.
The extra travel time is more than 60 minutes.
This will take until approximately 6:30 PM hours. -
Update
Between Winschoten and Weener no trains are running due to a defective railway track.
The extra travel time is more than 60 minutes.
This will take until at least 6:30 PM hours. -
Update
Between Zuidbroek and Scheemda no trains are running due to a signal failure.
Between Winschoten and Weener no trains are running due to a signal failure.
The extra travel time is more than 60 minutes.
This will take until at least 5:15 PM hours.Advice
Express buses are running between Zuidbroek and Scheemda.
Train measures
- Stoptrein 37500 Groningen - Winschoten - Bad Nieuweschans is cancelled between Zuidbroek and Winschoten
-
Update
Between Zuidbroek and Scheemda no trains are running due to a signal failure.
The extra travel time is more than 60 minutes.
This will take until at least 5:15 PM hours.Advice
Express buses are running between Zuidbroek and Scheemda.
Train measures
- Stoptrein 37500 Groningen - Winschoten - Bad Nieuweschans is cancelled between Zuidbroek and Winschoten
-
Update
Between Zuidbroek and Winschoten no trains are running due to a signal failure.
The extra travel time is more than 60 minutes.
This will take until at least 5:15 PM hours.Advice
Express buses are running between Zuidbroek and Scheemda.
Train measures
- Stoptrein 37500 Groningen - Winschoten - Bad Nieuweschans is cancelled between Zuidbroek and Winschoten
-
Update
Between Zuidbroek and Winschoten no trains are running due to a signal failure.
The extra travel time is more than 60 minutes.
This will take until at least 5:15 PM hours.Train measures
- Stoptrein 37500 Groningen - Winschoten - Bad Nieuweschans is cancelled between Zuidbroek and Winschoten
-
Update
Between Zuidbroek and Winschoten no trains are running due to a signal failure.
The extra travel time is more than 60 minutes.
It is not known yet how long this will take.Train measures
- Stoptrein 37500 Groningen - Winschoten - Bad Nieuweschans is cancelled between Zuidbroek and Winschoten
-
Update
Between Zuidbroek and Scheemda no trains are running due to a signal failure.
The extra travel time is more than 60 minutes.
It is not known yet how long this will take. -
Disruption
Between Groningen and Leer (Ostfriesl) no trains are running due to a signal failure.
The extra travel time is more than 60 minutes.
It is not known yet how long this will take.
More about this disruption
Statistics
This disruption started at 3:32 PM on September 28, 2018 and took 2 hours, 58 minutes in total.
For statistics, this disruption is caused due to a defective railway track.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by Arriva.
Got delayed due to this disruption? You may be reimbursed.