  1. Disruption resolved Last update

    Between Amsterdam Centraal and Leiden Centraal the restrictions are resolved.

  2. Delays decreasing

    Between Amsterdam Centraal and Leiden Centraal the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 10:00 PM hours.

  3. Update

    Between Amsterdam Centraal and Leiden Centraal fewer Sprinter trains are running due to damaged overhead wires.
    The extra travel time is about 15 minutes.
    This will take until approximately 10:00 PM hours.

    Train measures

    • Sprinter 4600 Den Haag C. - Schiphol Airport - Amsterdam C. is cancelled between Leiden Centraal and Amsterdam Centraal
  4. Update

    From and to Schiphol Airport far fewer trains are running due to damaged overhead wires.
    This will take until approximately 10:30 PM hours.

    Train measures

    • Intercity direct 900 Amsterdam C. - Schiphol Airport - Rotterdam C. - Breda is cancelled between Rotterdam Centraal and Amsterdam Centraal
    • Intercity direct 1000 Amsterdam C. - Schiphol Airport - Rotterdam C. is cancelled between Amsterdam Centraal and Rotterdam Centraal
    • Intercity 1600 Schiphol Airport - Amersfoort - Hengelo - Enschede is cancelled between Schiphol Airport and Hilversum
    • Intercity 2400 Lelystad C. - Schiphol Airport - Rotterdam C. - Dordrecht is cancelled between Almere Centrum and Den Haag Centraal
    • Sprinter 4600 Den Haag C. - Schiphol Airport - Amsterdam C. is cancelled between Leiden Centraal and Amsterdam Centraal
    • Sprinter 5700 Utrecht C. - Hilversum - Hoofddorp is cancelled between Amsterdam Zuid and Hoofddorp
    • Sprinter 5800 Hoofddorp - Amsterdam C. is cancelled between Amsterdam Centraal and Hoofddorp
    • Intercity 11600 Schiphol Airport - Amersfoort - Schothorst is cancelled between Hilversum and Schiphol Airport
  5. Update

    From and to Schiphol Airport far fewer trains are running due to damaged overhead wires.
    This will take until approximately 9:15 PM hours.

    Train measures

    • Intercity direct 900 Amsterdam C. - Schiphol Airport - Rotterdam C. - Breda is cancelled between Rotterdam Centraal and Amsterdam Centraal
    • Intercity direct 1000 Amsterdam C. - Schiphol Airport - Rotterdam C. is cancelled between Amsterdam Centraal and Rotterdam Centraal
    • Intercity 1600 Schiphol Airport - Amersfoort - Hengelo - Enschede is cancelled between Schiphol Airport and Hilversum
    • Intercity 2400 Lelystad C. - Schiphol Airport - Rotterdam C. - Dordrecht is cancelled between Almere Centrum and Den Haag Centraal
    • Sprinter 4600 Den Haag C. - Schiphol Airport - Amsterdam C. is cancelled between Leiden Centraal and Amsterdam Centraal
    • Sprinter 5700 Utrecht C. - Hilversum - Hoofddorp is cancelled between Amsterdam Zuid and Hoofddorp
    • Sprinter 5800 Hoofddorp - Amsterdam C. is cancelled between Amsterdam Centraal and Hoofddorp
    • Intercity 11600 Schiphol Airport - Amersfoort - Schothorst is cancelled between Hilversum and Schiphol Airport
  6. Update

    From and to Schiphol Airport far fewer trains are running due to damaged overhead wires.
    This will take until approximately 9:15 PM hours.

  7. Update

    From and to Schiphol Airport there is a service disruption due to damaged overhead wires.
    This will take until approximately 8:45 PM hours.

  8. Disruption

    From and to Schiphol Airport there is a service disruption due to damaged overhead wires.
    Updates will follow as more information becomes available.

More about this disruption

Statistics

This disruption started at 7:52 PM on December 4, 2018 and took 1 hour, 50 minutes in total.

For statistics, this disruption is caused due to damaged overhead wires.

Operators

This disruption affects trains operated by NS, NS International, Thalys and Eurostar.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights