Large signalling and points failure: Breda (18 January 2019)
-
Disruption resolved Last update
From and to Breda the restrictions are resolved.
-
Delays decreasing
From and to Breda the restrictions are resolved.
Delays are decreasing.
This will take until approximately 12:15 AM on Saturday, January 19, 2019. -
Update
From and to Breda no trains are running due to a large signalling and points failure.
This will take until approximately 12:15 AM on Saturday, January 19, 2019.Train measures
- Intercity direct 900 Amsterdam C. - Schiphol Airport - Rotterdam C. - Breda is cancelled between Breda and Amsterdam Centraal
- Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Rotterdam Centraal and Tilburg
- Intercity 2800 Rotterdam C. - Utrecht C. is cancelled between Rotterdam Centraal and Utrecht Centraal
- Intercity 3600 Zwolle - Deventer - Nijmegen - Roosendaal is cancelled between Roosendaal and Tilburg
- Sprinter 6500 Utrecht C. - Castellum is cancelled between Utrecht Centraal and Houten Castellum
- Sprinter 6600 Dordrecht - Breda - 's-Hertogenbosch - Arnhem C. is cancelled between Lage Zwaluwe and 's-Hertogenbosch
-
Update
From and to Breda no trains are running due to a large signalling and points failure.
This will take until approximately 12:30 AM on Saturday, January 19, 2019.Train measures
- Intercity direct 900 Amsterdam C. - Schiphol Airport - Rotterdam C. - Breda is cancelled between Breda and Amsterdam Centraal
- Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Rotterdam Centraal and Tilburg
- Intercity 2800 Rotterdam C. - Utrecht C. is cancelled between Rotterdam Centraal and Utrecht Centraal
- Intercity 3600 Zwolle - Deventer - Nijmegen - Roosendaal is cancelled between Roosendaal and Tilburg
- Sprinter 6500 Utrecht C. - Castellum is cancelled between Utrecht Centraal and Houten Castellum
- Sprinter 6600 Dordrecht - Breda - 's-Hertogenbosch - Arnhem C. is cancelled between Lage Zwaluwe and 's-Hertogenbosch
-
Update
From and to Breda no trains are running due to a large signalling and points failure.
This will take until approximately 12:30 AM on Saturday, January 19, 2019.Train measures
- Intercity direct 900 Amsterdam C. - Schiphol Airport - Rotterdam C. - Breda is cancelled between Breda and Amsterdam Centraal
- Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Rotterdam Centraal and Tilburg
- Intercity 2800 Rotterdam C. - Utrecht C. is cancelled between Rotterdam Centraal and Utrecht Centraal
- Intercity 3600 Zwolle - Deventer - Nijmegen - Roosendaal is cancelled between Roosendaal and Tilburg
- Sprinter 5000 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Rotterdam Centraal and Den Haag Centraal
- Sprinter 6500 Utrecht C. - Castellum is cancelled between Utrecht Centraal and Houten Castellum
- Sprinter 6600 Dordrecht - Breda - 's-Hertogenbosch - Arnhem C. is cancelled between Lage Zwaluwe and 's-Hertogenbosch
-
Update
From and to Breda no international trains are running due to a large signalling and points failure.
The extra travel time is more than 30 minutes.
This will take until approximately 12:30 AM on Saturday, January 19, 2019.Train measures
- Intercity direct 900 Amsterdam C. - Schiphol Airport - Rotterdam C. - Breda is cancelled between Breda and Amsterdam Centraal
- Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Rotterdam Centraal and Tilburg
- Intercity 2800 Rotterdam C. - Utrecht C. is cancelled between Rotterdam Centraal and Utrecht Centraal
- Intercity 3600 Zwolle - Deventer - Nijmegen - Roosendaal is cancelled between Roosendaal and Tilburg
- Sprinter 5000 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Rotterdam Centraal and Den Haag Centraal
- Sprinter 6500 Utrecht C. - Castellum is cancelled between Utrecht Centraal and Houten Castellum
- Sprinter 6600 Dordrecht - Breda - 's-Hertogenbosch - Arnhem C. is cancelled between Lage Zwaluwe and 's-Hertogenbosch
-
Disruption
From and to Breda no international trains are running due to a large signalling and points failure.
The extra travel time is more than 30 minutes.
This will take until approximately 12:30 AM on Saturday, January 19, 2019.
More about this disruption
Statistics
This disruption started at 10:22 PM on January 18, 2019 and took 1 hour, 54 minutes in total.
For statistics, this disruption is caused due to a large signalling and points failure.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS, NS International and NMBS.
Got delayed due to this disruption? You may be reimbursed.