sein- en wisselstoring

Large signalling and points failure: Breda (11 February 2019)

  1. Disruption resolved Last update

    From and to Breda the restrictions are resolved.

  2. Delays decreasing

    From and to Breda the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 10:00 AM hours.

  3. Update

    From and to Breda no international trains are running due to a large signalling and points failure.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 10:15 AM hours.

  4. Update

    From and to Breda no international trains are running due to a disruption elsewhere.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 10:15 AM hours.

  5. Disruption

    From and to Breda no trains are running due to a disruption elsewhere.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 10:15 AM hours.

More about this disruption

Statistics

This disruption started at 8:23 AM on February 11, 2019 and took 1 hour, 39 minutes in total.

For statistics, this disruption is caused due to a large signalling and points failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS, NS International and NMBS.