Signal and level crossing failure: Roosendaal-Vlissingen (3 April 2019)

  1. Disruption resolved Last update

    Between Bergen op Zoom and Kruiningen-Yerseke the restrictions are resolved.

    Advice

    Buses are still running between Bergen op Zoom, Rilland-Bath, Krabbendijke and Kruiningen-Yerseke.

  2. Delays decreasing

    Between Bergen op Zoom and Kruiningen-Yerseke the restrictions are resolved.
    Delays are decreasing.
    This will take until approximately 3:30 PM hours.

    Advice

    Buses are still running between Bergen op Zoom, Rilland-Bath, Krabbendijke and Kruiningen-Yerseke.

  3. Delays decreasing

    Between Bergen op Zoom and Kruiningen-Yerseke the restrictions are resolved.
    Delays are decreasing.
    This will take until approximately 4:00 PM hours.

    Advice

    Buses are still running between Bergen op Zoom, Rilland-Bath, Krabbendijke and Kruiningen-Yerseke.

  4. Update

    Between Bergen op Zoom and Kruiningen-Yerseke no trains are running due to a signal and level crossing failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 4:00 PM hours.

    Advice

    Buses are running between Bergen op Zoom, Rilland-Bath, Krabbendijke and Kruiningen-Yerseke.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Kruiningen-Yerseke and Bergen op Zoom
  5. Update

    Between Bergen op Zoom and Kruiningen-Yerseke no trains are running due to a signal and level crossing failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 4:30 PM hours.

    Advice

    Buses are running between Bergen op Zoom, Rilland-Bath, Krabbendijke and Kruiningen-Yerseke.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Kruiningen-Yerseke and Bergen op Zoom
  6. Update

    Between Bergen op Zoom and Kruiningen-Yerseke there are delays and fewer trains are running due to a signal and level crossing failure.
    This will take until approximately 4:00 PM hours.

    Advice

    Buses are running between Bergen op Zoom, Rilland-Bath, Krabbendijke and Kruiningen-Yerseke.

  7. Delays decreasing

    Between Bergen op Zoom and Kruiningen-Yerseke the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 2:30 PM hours.

  8. Update

    Between Bergen op Zoom and Kruiningen-Yerseke there are delays and fewer trains are running due to a signal and level crossing failure.
    This will take until approximately 4:00 PM hours.

  9. Delays decreasing

    Between Bergen op Zoom and Kruiningen-Yerseke the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 1:30 PM hours.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Kruiningen-Yerseke and Bergen op Zoom
  10. Update

    Between Bergen op Zoom and Kruiningen-Yerseke no trains are running due to a signal and level crossing failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 1:30 PM hours.

    Advice

    Local buses are running between Bergen op Zoom, Rilland-Bath, Krabbendijke and Kruiningen-Yerseke.
    Express buses are running between Bergen op Zoom and Kruiningen-Yerseke.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Kruiningen-Yerseke and Bergen op Zoom
  11. Update

    Between Bergen op Zoom and Kruiningen-Yerseke no trains are running due to a signal and level crossing failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 12:30 PM hours.

    Advice

    Express buses are running between Bergen op Zoom and Kruiningen-Yerseke.
    Local buses are running between Bergen op Zoom, Rilland-Bath, Krabbendijke and Kruiningen-Yerseke.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Kruiningen-Yerseke and Bergen op Zoom
  12. Update

    Between Bergen op Zoom and Kruiningen-Yerseke no trains are running due to a signal and level crossing failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 11:30 AM hours.

    Advice

    Local buses are running between Bergen op Zoom, Rilland-Bath, Krabbendijke and Kruiningen-Yerseke.
    Express buses are running between Bergen op Zoom and Kruiningen-Yerseke.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Kruiningen-Yerseke and Bergen op Zoom
  13. Update

    Between Bergen op Zoom and Kruiningen-Yerseke no trains are running due to a signal and level crossing failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 11:30 AM hours.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Kruiningen-Yerseke and Bergen op Zoom
  14. Update

    Between Bergen op Zoom and Kruiningen-Yerseke no trains are running due to a signal and level crossing failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 11:30 AM hours.

  15. Disruption

    Between Bergen op Zoom and Kruiningen-Yerseke there is a service disruption due to a signal and level crossing failure.
    Updates will follow as more information becomes available.

More about this disruption

Statistics

This disruption started at 8:51 AM on April 3, 2019 and took 6 hours, 41 minutes in total.

For statistics, this disruption is caused due to a signal and level crossing failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.