Signal failure: Utrecht-Rotterdam; Utrecht-Den Haag (21 May 2019)
-
Disruption resolved Last update
Between Utrecht Centraal and Vleuten the restrictions are resolved.
-
Delays decreasing
Between Utrecht Centraal and Vleuten the restrictions are resolved.
Delays are decreasing.
Service is normal around 7:00 AM hours. -
Update
Between Utrecht Centraal and Vleuten far fewer trains are running due to a signal failure.
This will take until approximately 7:30 AM hours.Train measures
- Intercity 1700 Den Haag C. - Amersfoort - Hengelo - Enschede is cancelled between Den Haag Centraal and Utrecht Centraal
- Intercity 2000 Den Haag C. - Utrecht C. is cancelled between Den Haag Centraal and Utrecht Centraal
- Intercity 2800 Rotterdam C. - Utrecht C. is cancelled between Rotterdam Centraal and Utrecht Centraal
- Sprinter 6000 Woerden - Utrecht C. - Tiel is cancelled between Woerden and Utrecht Centraal
- Sprinter 6500 Utrecht C. - Castellum is cancelled between Utrecht Centraal and Houten Castellum
- Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Den Haag Centraal and Utrecht Centraal
-
Update
Between Utrecht Centraal and Vleuten far fewer trains are running due to a signal failure.
This will take until approximately 7:30 AM hours.Train measures
- Intercity 1700 Den Haag C. - Amersfoort - Hengelo - Enschede is cancelled between Den Haag Centraal and Utrecht Centraal
- Intercity 2000 Den Haag C. - Utrecht C. is cancelled between Den Haag Centraal and Utrecht Centraal
- Intercity 2800 Rotterdam C. - Utrecht C. is cancelled between Rotterdam Centraal and Utrecht Centraal
- Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Den Haag Centraal and Utrecht Centraal
-
Update
Between Vleuten and Utrecht Leidsche Rijn far fewer trains are running due to a signal failure.
This will take until approximately 7:30 AM hours. -
Update
Between Vleuten and Utrecht Leidsche Rijn far fewer trains are running due to a signal failure.
This will take until approximately 7:00 AM hours. -
Disruption
From and to Vleuten no trains are running due to a cause yet unknown.
Updates will follow as more information becomes available.
More about this disruption
Statistics
This disruption started at 4:47 AM on May 21, 2019 and took 2 hours, 10 minutes in total.
For statistics, this disruption is caused due to a signal failure.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.