Signal failure: Leiden-Den Haag C (29 May 2019)
-
Disruption resolved Last update
Between Leiden Centraal and Den Haag Centraal the restrictions are resolved.
-
Delays decreasing
Between Leiden Centraal and Den Haag Centraal the restrictions are resolved.
Delays are decreasing.
This will take until approximately 8:15 PM hours. -
Update
Between Leiden Centraal and Den Haag Centraal there are fewer trains running due to a signal failure.
This will take until approximately 8:15 PM hours. -
Disruption
Between Den Haag Mariahoeve and Den Haag Centraal there are fewer trains running due to a signal failure.
This will take until approximately 8:15 PM hours.
More about this disruption
Statistics
This disruption started at 6:51 PM on May 29, 2019 and took 1 hour, 24 minutes in total.
For statistics, this disruption is caused due to a signal failure.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.