uitloop werkzaamheden

Over-running engineering works: Dordrecht-Breda (12 July 2019)

  1. Disruption resolved Last update

    Between Dordrecht and Breda the train traffic is fully resumed.

    Train measures

    • Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Breda and Tilburg
    • Intercity 2300 Dordrecht - Breda is cancelled between Breda and Dordrecht
  2. Delays decreasing

    Between Dordrecht and Breda the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 8:30 AM hours.

    Train measures

    • Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Breda and Tilburg
    • Intercity 2300 Dordrecht - Breda is cancelled between Breda and Dordrecht
  3. Update

    Between Dordrecht and Breda no intercities are running due to over-running engineering works.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 8:30 AM hours.

    Train measures

    • Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Breda and Tilburg
    • Intercity 2300 Dordrecht - Breda is cancelled between Breda and Dordrecht
  4. Update

    Between Dordrecht and Breda no intercities are running due to over-running engineering works.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 8:30 AM hours.

    Train measures

    • Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Breda and Tilburg
    • Intercity 2300 Dordrecht - Breda is cancelled between Breda and Dordrecht
    • Intercity 3600 Zwolle - Deventer - Nijmegen - Roosendaal is cancelled between Breda and Tilburg
    • Sprinter 5200 Tilburg Uni. - Eindhoven is cancelled between Tilburg Universiteit and Tilburg
    • Sprinter 6600 Dordrecht - Breda - 's-Hertogenbosch - Arnhem C. is cancelled between Gilze-Rijen and 's-Hertogenbosch
  5. Disruption

    Between Dordrecht and Breda no intercities are running due to over-running engineering works.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 8:30 AM hours.

    Train measures

    • Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Breda and Tilburg
    • Intercity 3600 Zwolle - Deventer - Nijmegen - Roosendaal is cancelled between Breda and Tilburg
    • Sprinter 5200 Tilburg Uni. - Eindhoven is cancelled between Tilburg Universiteit and Tilburg
    • Sprinter 6600 Dordrecht - Breda - 's-Hertogenbosch - Arnhem C. is cancelled between Gilze-Rijen and 's-Hertogenbosch

More about this disruption

Statistics

This disruption started at 5:32 AM on July 12, 2019 and took 3 hours in total.

For statistics, this disruption is caused due to over-running engineering works.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights